Construction Update 12/20/18

Most major work is complete on the project! Thank you to neighbors for your patience as we have constructed these improvements in your neighborhood!

Emery continues to make progress on remaining “punch-list” items, and expects to be substantially complete with restoration by early next week. Additionally, final tweaks are being made to certain areas of the project following the recent heavy rain events.

In early December, crews took advantage of a break in the weather to stripe the new stop bars and approaches.

Parking aggregate has been placed in the parking areas along D Avenue. Street name signs are expected to be reinstalled in the coming weeks – crews are waiting on a particular part, which has delayed their placement.

The landscapers have really ramped up their activities the past few weeks. Soil and mulch has been placed in most of the new landscaped areas and stormwater planters.

Large shipments of plants and trees are arriving and being installed throughout the corridor, helping to put the finishing touches on the new street and complete the transformation! Crews are aiming to finish planting by early January.

D Avenue between State and 1st Street remains closed at Highway 43 until major landscaping is complete in that block. Access is maintained for residents via 1st Street.

In observance of Christmas Day and New Year’s Day, no work will take place on December 25 or January 1. All work is expected to be complete in early-mid January.