Project Schedule

Overall Work Plan

Construction started in early May 2018 and is expected to continue through late 2018. Construction schedules change frequently due to weather, issues in the field, and other variables. For the latest information, visit the project updates page or sign-up to the e-newsletter.

Emery and Son’s (general contractor) underground utility work was completed in early July. Major road reconstruction work began in mid-July, which resulted in a full 24/7 road closure until late August.

Through fall 2018, crews will pour the sidewalk, place the final asphalt and construct the stormwater planters. The final activity would be planting the final landscaping and installing the lighting.

 

Unfortunately, construction is disruptive, especially to those nearest the work. The project includes stormwater and waterline installation, roadway demolition, roadway surface preparation and grading, concrete formwork, concrete placement, concrete curing, asphalt paving and significant landscape and irrigation work. This means crews will be in front of each property along D Avenue many times over the project duration.

We appreciate all neighbors abiding by traffic control signage and avoiding active construction areas for the safety of all.

For more information about what to expect during construction, review the March 2018 newsletter.

The City and contractor will strive to keep neighbors aware of the ever-changing construction activities. The best way to stay up to date is by signing up to our email listserv or visiting our project updates page. If you have a special access need we should be aware of, please contact us.

 

 

 

Designing for stormwater, pedestrian, and pavement needs