Cervantes Emergency Water Line Repair

Project Background/Summary

Emergency roadway and utility repair and replacement caused by a water main break that occurred on Cervantes Street, August 30, 2013. Work will include extensive roadway reconstruction, waterline replacement, and potentially trench replacement for wastewater and stormwater facilities. Project not budgeted in the CIP, however, there is currently $230,000 available for waterline rehabilitation, undefined location.

If you would like more information about this project, please contact David Kudna, Project Manager at  email.

Updates

June 16, 2015
Planned Water Shutdown on Cervantes
4:00 PM

The Contractor is 95% complete with the connection plan. The Contractor has seven connections to complete tomorrow.

If you have any questions or concerns please call David Kudna, Project Manager at 503-319-1882.

 

 

June 16, 2015
Planned Water Shutdown on Cervantes
12:00 PM

Emery is currently 75 percent through their connection plan. They are working in the area of 240 Cervantes and moving to the east.

If you have any questions or concerns please call David Kudna, Project Manager at 503-319-1882.

 

June 15, 2015
Planned Water Shutdown on Cervantes

4:00 PM

The Contractor finished up in the area of 260 Cervantes. They will continue tomorrow morning at 7:00 AM where they left off today.  Please check back tomorrow for additional updates.

As always, if you have any questions please feel to contact me.

 

12:00 PM
Good News!  The water connections are progressing as planned.  Emery is currently midway through their connection plan. They are working in the area of 260 Cervantes and moving to the east.

If you have any questions or concerns please call David Kudna, Project Manager at 503-319-1882.

 

June 12, 2015

Planned Water Shutdown On Cervantes
June 15 and 16

As part of the Lake Oswego - Cervantes Water Main Replacement Project, the Lake Oswego Water Department and Emery and Sons have coordinated a plan to shut off  the water in order to make necessary connections to the water systems.

If you have received a Door Hanger Notice that your water will be turned off, please see the details below:

  • Water will be shut off to your premises between 8 a.m. and 4 p.m. on Monday, June 15 or Tuesday, June 16.
  • Immediately prior to shut off, Emery will knock on your door to notify you of the shutdown. If they do not get a response they will proceed with the shutdown.
  • Service will be restored no later than 4 hours after it has been shut off at your premises.
  • Please do not use any water for drinking or cooking during the time that the water is shut off.
  • Please visit the website on Monday and Tuesday for additional updates.

June 3, 2015

The water shut down has been postponed until further notice. If you would like more information, please contact David Kudna, Project Manager at 503.534.5299.

June 2, 2015

Planned Water Shutdown On Cervantes
June 4th and 5th

As part of the Lake Oswego - Cervantes Water Main Replacement Project, the Lake Oswego Water Department and Emery and Sons have coordinated a plan to shut off  the water in order to make necessary connections to the water systems. 

If you have received a Door Hanger Notice that your water will be turned off, please see the details below:

  • Water will be shut off to your premises between 8:00 am and 4:00 pm on Thursday, June 4th and Friday, June 5th.
  • Service will be restored in approximately 4 hours after it has been shut off at your premises.
  • Please do not use any water for drinking or cooking during the time that the water is shut off.
  • Tip: Before your water is shut off, fill a couple of 5-gallon buckets with water.  This water can be used to flush toilets, washing hands, or for cooking and drinking.

The Lake Oswego Water Department and Emery and Sons apologize for any inconvenience this may cause.

May 28 2015

Cervantes Paving Scheduled for Tomorrow, May 29th

  • The Contractor is prepping the roadway for paving which is scheduled for tomorrow. Due to the heavy construction activity on the east end of Cervantes the roadway is currently closed to through traffic, please use the West entrance until paving is complete tomorrow evening.

May 14, 2015

The City and the Contractor thank you for your patience and your cooperation during construction.  The project is ahead of schedule and nearing completion. 

  • Emery and Sons Construction Group has completed main line and service installations.
  • Permanent trench patch will be complete today.
  • Contractor will be installing the water main across the ravine today.
  • We anticipate the Contractor will rebuild the damaged sections of Cervantes next week.  Please do not park within the rebuild section, which starts roughly at 206 Cervantes and continues down to Jefferson Parkway.

April 8, 2015

  • Emery and Sons Construction Group will begin constructing the water main replacement starting Monday, April 10, 2015, which will include opening trenching in Cervantes.
  • The Contractor will post no-parking signs delineating the work zone
  • The Contractor will provide access to driveways within the work zone.

March 24, 2015

The Cervantes Water Main Replacement project is moving into the construction phase.

  • Sealed proposals were received for WO 187 - Cervantes Water Main Replacement Project for the City of Lake Oswego. Proposals were received by David Kudna, Project Manager, on February 18, 2015, 2:00 PM, local time. The apparent low bidder was Emery & Sons Construction Group.
  • The Lake Oswego City Council awarded the construction contract to Emery and Sons Construction Group on March 3, 2015.
  • The Contractor will begin mobilization the week of April 6th.
  • Typical construction hours  are Monday - Friday, 7:00 am to 6:00 pm.
  •  The project limits are from 335 Cervantes to the east connection with Jefferson Parkway.
  • Sections of Cervantes Road will be closed to through traffic during construction. Closures will be updated throughout project.  Please check back for updates.

 