Skip to Main Content
City of Lake Oswego
Public Works Banner

Marylhurst Pump Station Replacement Project

Project Background/Summary

In September 2016, the City of Lake Oswego hired a consultant team – Murraysmith - to conduct the design for replacement of the Marylhurst Sewage Pump Station.

The Marylhurst Pump Station was constructed in the early 1980s and is the city’s second largest station.  It has a service area of 347 acres, which is 83% residential (more than 1,200 households).

The pump station is located along the westerly bank of the Willamette River, at the north end of Old River Road near Glenmorrie Drive, adjacent to the river pathway.

Project Description

The current station has aging equipment with expensive repair and maintenance costs, and is unreliable in emergencies. It has a history of overflow events and there is no permanent back-up power currently at the site. Access into the pump station dry well (underground pump and electrical controls chamber) is by an elevator within a 3-foot diameter entrance tube and is considered “confined space entry”., Therefore, access is restricted which makes it difficult to maintain the station. Also, below grade electrical equipment is vulnerable to flooding.

The project will involve replacing the existing 37-year old pump station in the same location. New high efficiency pumps will be installed and equipment will be configured differently to provide safer access for operations and maintenance staff, and bring the station up to current standards. A permanent on-site generator will be added to increase the reliability of the pump station. Electrical panels will also be placed within an above-ground building for security and protection. The project team will incorporate neighborhood feedback into design of the architectural features of the building landscaping.

Updates

January 2018

An open house was held on January 10, 2018 to share information and gather feedback on site landscaping and architectural features for the new electrical control building. View the displays here.

December 2017

Design is currently underway on the replacement project. An open house will be held on January 10, 2018 where the project team will share information and gather public feedback on site landscaping and architectural features for the new electrical control building.

Wednesday, Jan. 10, 2018
6:30 – 8:30 p.m. (drop by anytime between these hours)
Marylhurst University,
Willow Room
17600 Pacific Hwy.,
Lake Oswego

Boards will display alternate architectural materials, landscaping and hardscaping features proposed for the project. Input and feedback received at the open house will enable the team to refine the final design before submitting a land-use application to the city’s planning department.

Design and permitting are expected to continue through summer 2018; construction is anticipated to start in fall 2018.

May 2017

The project team presented an overview and update about the design of the project to the Glenmorrie Neighborhood Association on May 23, 2017. The slides are available here.  

October 2016

From October 3 through October 7, 2016, as a part of the pre-design work for the project, crews will drill 5 or 6 strategically located test holes along the Willamette River Pathway between the lower parking lot of George Rogers Park and Old River Road. The pipeline from the Marylhurst Pump Station, that conveys wastewater to a manhole in Furnace Street, is buried along the entire length of the pathway. The borings will help to determine the ability of the pathway and footbridges to continue supporting the pipeline during a significant seismic event.  To maintain safety, the pathway will be closed to public use, 24/7, during those five days.

 Surveying and other topographic fieldwork will also be conducted during early October 2016.

ID

WO 238

Type

Capital Improvement Projects

Contact Us

Pat McDougal, P.E., Project Manager
pmcdougal@ci.oswego.or.us
503-635-0273

Status

Active