Agenda Item - 2002-05-21 - Number 4.2.4 - 4.2.4 05/21/02 CITY OF LAKE OSWEGO AGENDA REPORT SUMMARY MEETING DATE: May 21, 2002 SUBJECT: Award of a Public Improvement Contract for the 2002 Pavement Management Program, Phase 2 -Slurry Seals (Work Order 1163) RECOMMENDED MOTION: Move to award a public improvement contract to Blackline, Inc. in the amount of$69,098.56 for construction of the 2002 Pavement Management Program, Phase 2 - Slurry Seals (Work Order 1163). EST. FISCAL ATTACHMENTS: NOTICED (Date): IMPACT: $69,098.56 • Komarek Council Report dated May 13, 2002 STAFF COST: Ordinance no.: NA BUDGETED: Y X N Resolution no.: NA FUNDING SOURCE: Previous Council Street Fund consideration: None 6. or,..,..---k, .., 44' CENGINE R COMM. DEV.. DIRECTOR CITY NAGER Ch 14 2- 5/14"-/C=)-2._ 7 47( 4.7 6.(__ Date Date Date 23 H:\Kathy_g\WO\1163\Phase 2\WO 1163 Agenda Report.doc ``,L�co LAKE OSCO iiiiiiv‘114117 CITY OF LAKE OSWEGO COUNCIL REPORT OREGo$ TO: Douglas J. Schmitz, City Manager FROM: Joel B. Komarek, Acting City Engineer' PREPARED BY: George Dwire, Construction Supervisor yJ/11ti SUBJECT: Recommendation of Bid Award for Construction of Work Order 1163, 2002 Pavement Management Program,Phase 2 - Slurry Seals DATE: May 13, 2002 Action The City Council is requested to award a public improvement contract to Blackline, Inc. in the amount of$69,098.56 for the 2002 Pavement Management Program, Phase 2 - Slurry Seals. Introduction This Contract requires Council award in order to comply with City and State contracting and purchasing procedures. Funding for this project is predicated upon adoption of the FY 2002-03 budget. Discussion At 10:00 a.m., on Wednesday, May 8, 2002, the City of Lake Oswego opened bids for the above referenced project. Two bids were received with the apparent low bid being submitted by Blackline, Inc. The bidders and the amount of their bids are tabulated below: Bidder Bid Blackline, Inc. $69,098.56 Asphalt Maintenance Associates, Inc. $72,967.87 Engineer's Estimate $87,153.89 25 Council Report May 13, 2002 Page 2 of 2 Based upon a review of the bids by staff, the bid submitted by Blackline, Inc. was deemed responsive and responsible. Alternatives The alternatives are to: 1) award the contract or 2) reject all bids and re-bid the project. Conclusion City staff prepared the bidding documents for this project in accordance with the City's requirements for public improvement contracts. The bidding process was conducted in accordance with the City's public contracting procedures. Staff, therefore, recommends that Council award the contract to Blackline, Inc. in the amount of$69,098.56. H\Kathyg\WO\1163\Phase 2\WO 1163 Phase-2 Council Report doc