Exploratory Digging Work: Boones Ferry Road, Lanewood St, Douglas Circle, Twin Fir Road, Upper Drive, Iron Mountain Blvd. and Chandler Road
Beginning in mid December, crews will be working along the proposed water pipeline route that runs east from Lake Grove School and Boones Ferry Road along Lanewood Street, Douglas Circle, Twin Fir Road, Upper Drive, Iron Mountain Boulevard and Chandler Road. They will dig small holes in the roadway to locate all underground utilities and pipes, to ensure the pipeline route does not conflict with existing utilities.
Workers will use a vacuum truck and small excavator, digging holes 50 to 150 feet apart as they travel along the pipeline route. Holes will be repaired as work progresses. Work is expected to continue through the end of January 2014.
The following table outlines key locations and approximate timeframes for the digging work.
| Where will crews be? | When? |
|---|---|
|
Lanewood Street |
Mid - late December |
|
Lower Douglas Circle |
Late December |
| Lake Grove School and Boones Ferry Road | School Winter Break, late December - early January 2014 |
| Twin Fir Road (between Upper Drive and Douglas Circle) | Early January 2014 |
| Upper Drive (between Iron Mtn. Blvd and Twin Fir Drive) | Early - mid January |
| Iron Mountain Blvd | Mid - late January 2014 |
| Chandler Road (between Iron Mtn. Blvd and 10th Street) | Late January 2014 |
The work will occur between 7:00 a.m. and 3:30 p.m. There will be single-lane closures to accommodate equipment. Some narrow streets may be temporarily closed to through traffic during work hours, with access restricted to local residents during this time. Roads will be repaired after work is complete. Please watch for flaggers.
We apologize for the inconvenience this may cause.
For more details about the work west of Boones Ferry road, read the pipeline construction update newsletter (Nov. 2013). For other information, please email lotwater@ci.oswego.or.us, call the hotline at 503-697-6502.

