Construction Update 11/8/19

New Traffic Shift Coming in Mid-November

Weather permitting, starting the week of 11/18, the work zone is expected to expand further north. The current temporary traffic configuration on Boones Ferry Road from W. Sunset Drive to Bryant Road will be extended to Reese Road (at the post office).

Aerial image looking of Boones Ferry Road looking north from Bryant Road

Some existing striping will be removed and new temporary striping placed. Instead of four lanes there will be three: one lane in each direction, plus a center turn lane. Traffic will be shifted to the west side of the road while crews work on the east side. This traffic change will give crews room to maneuver and still keep the road open, but at times there will be flaggers and brief delays with equipment.

Click here to watch a video about this upcoming traffic change.

Once this new work zone is set up on Boones Ferry Road between Bryant and Reese Road, crews will begin installing a new gas line, illumination conduit, water line and stormwater line on the east side (Healthy Pet/Car Wash side).

Multiple Crews Working Day and Night

Crews are installing the handful of remaining utility vaults for the first section of the undergrounding, between Madrona and Bryant Roads. They are also installing retaining walls, new illumination poles and signal poles, and grading and preparing the area for pouring new curbs in early December. NW Natural Gas is also installing gas lines and services.

Crews placing fabric, rock and grading the work zone in preparation for new curbs.

Utility companies (Comcast, Centurylink, Wave, PGE, CBX) will now arrive to begin pulling their lines through the newly installed conduit, configuring their vaults, switching over services, and eventually removing the above ground power poles. This utility switch over operation is expected to continue through early 2020. Some of this work will take place during the day, and some at night. Any planned shutdowns for customers will be coordinated by the utility companies.

Conduit, conduit and more conduit – part of the joint utility trench where the overhead wires will be relocated underground in these conduits.

Starting next week, crews expect to continue progressing north towards Oakridge Road on the underground joint utility trench, installing conduits and vaults on the west side of the road (Albertson’s/Banner Bank/Riccardo’s side). This work is expected to be conducted at night with lane closures and flaggers.

Stormlines

Work is almost complete on the new stormwater line on Boones Ferry Road, between Madrona and Bryant Road. During this night work, lanes are reduced and traffic is flagged 10 p.m. – 6 a.m. The signal at Bryant/Firwood/Boones Ferry is also flagged at night if crews are working close to the intersection.

Crews installing a stormwater person hole.

New and Temporary Signal Poles

New permanent signal pole foundations have been poured at the Madrona and Bryant intersections. Some have been installed at the new McDonald’s intersection. Next week, crews plan to pour the temporary signal pole foundations at Reese/Oakridge intersection at night. During this work, the signal will be shut down at night and traffic will be flagged.

Crews have installed the foundation and meter cabinet for the new speed radar feedback sign on Quarry Road. Mid-late next week they expect to install the final sign and connect the power. This work is expected to take one day to complete. Traffic will be flagged from 9 a.m. – 4 p.m.

Support Your Lake Grove Businesses During the Holiday Season!

Boones Ferry Road and all its businesses remain open during construction. This holiday season, please come out and support your friends and community businesses that make Lake Oswego a great place to live, work and play! Follow the blue cones and signs to access business driveways in the work zones.

In the next week, watch for the newest “Who’s Who on Boones Ferry Road” on our website and social media – this month we will be featuring Zupan’s Market!

Also, keep an eye out for our holiday videos on the City’s social media accounts over the coming weeks.

Enter the Shop Lake Grove Raffle

Our latest $100 raffle winner is Arva Bartos, a five-year patient at the Milan Center Chiropractic, pictured below with her Chiropractor Peter Milanovich.

Each month, we will be giving away TWO $100 gift cards to participating businesses located in the project area. Stop by one of these businesses to enter the raffle. Each month the raffle starts fresh, so keep coming back to visit your local businesses to enter.

If you are a business that is eligible and interested in participating in the Shop Lake Grove campaign, please complete this survey to sign up!

More Information?

For more information about schedule and work hours, click here.

You can also email info@boonesferryproject.org, call 503-697-6573 and follow the city on social media with #boonesferryproject and #followthebluecones.