Construction Update 3/13/20

Inspiring Future Engineers and Contractors

Our Boones Ferry Road project team inspired future civil engineers and construction contractors last week! 20 Lakeridge Middle School students participated in an all-day, hands-on learning experience and construction site visit with the project team, consultants and contractors. Watch this short video capturing the day.

This special event was also timely to showcase our unique, all-female City project team (Crystal Shum, Stacy Bluhm and Katy Kerklaan), as it was National Women in Construction Week! Hard hats off to the wonderful women who work in construction, public works and engineering services. You are paving the way for future women and young girls in engineering and construction!

Multiple Crews Working Throughout the Project

Due to the nature and scope of this project, there are multiple crews working throughout the entire corridor and on side streets – both day and night. Please plan extra time when traveling throughout the project area.

First Base Lift of Paving!

In late February, crews took advantage of some optimal weather, pouring the first base lift of asphalt on the west side of Boones Ferry Road between West Sunset Blvd. and Firwood Road, and portions of Bryant Road, Madrona Street and Firwood Road.

Earlier this week, crews also paved a new asphalt pathway on Lanewood Street (between First Citizens Bank and Boones Way).

A final overlay of asphalt and permanent striping will be installed at the end of the project.

In the coming weeks, crews will begin tearing out the existing sidewalk and preparing for new curbs and sidewalk along the Albertsons frontage on Firwood Road and Boones Ferry Road. They will also be preparing for curbs and sidewalk on the east side of Boones Ferry Road, between Oakridge and Bryant Road.

Undergrounding Operation

Next week, PGE crews are expected to arrive to the site to begin their switch from overhead to underground power in the southern area of the project. They will switch over services, and eventually remove the above ground power poles between Bryant and Madrona (the first segment). Some of this work is taking place during the day, and some at night.

The contractor is making good progress installing underground conduit and utility vaults, making their way towards the Oakridge Road/Reese Road intersection. This work will continue over the coming weeks and is being conducted at night. While crews are working in or near the intersection at night, the signal will be shut-off and traffic will be flagged.

NW Natural Gas has also been installing a new gas line and connections for customers.

Please note, any planned utility shutdowns for customers will be coordinated by the utility companies, and typically occur after business hours.

Stormwater Work

In the coming weeks, the contractor may start work on some miscellaneous stormwater pipe, access holes and planter facilities on Boones Ferry Road, north of Lanewood Street, and on Red Cedar Way, near the Kindercare. This work will most likely be conducted with a single lane closure from 9 a.m. – 3 p.m.

Illumination Poles and Signal Pole Foundations

The electrical subcontractor has started excavating to prepare for pouring signal pole foundations at the Lanewood Street (Lake Grove Elementary School) intersection, at McDonald’s and Reese Road. They are also installing illumination bases in the area between Bryant Road and Oakridge Road, on the west and east side of Boones Ferry Road. This work will continue over the next few weeks.

Who’s Who on Boones Ferry Road

This month’s Who’s Who on Boones Ferry Road features Riccardo’s Ristorante and Café Marzocca!

If you’ve lived, worked or visited in Lake Oswego in the last 40 years, chances are you’ve been to Riccardo’s Ristorante or Café Marzocca! Opened in 1980, Riccardo’s is a warm, family, Italian restaurant where patrons are treated more like family members than customers.

Watch the video featuring owners Georgette and Riccardo Spaccarelli share their passion for this community and for creating their own little part of Italy right here in Lake Oswego. They stay true to their Italian culture and cuisine, trying to turn your stomach into an Italian by using family recipes from Italy, serving only Italian wines and their favorite Italian coffee (Illy).

Click here to read more about Riccardo’s and Café Marzocca!

Shop Lake Grove Raffle Continues!

Our Shop Lake Grove monthly raffle continues!  Each month, we are giving away TWO $100 gift cards to participating businesses located in the project area. This month, winners selected Zupan’s and Riccardo’s for their gift cards.

Stop by one of these businesses to enter the raffle. Each month the raffle starts fresh, so keep coming back to visit your local businesses to enter.

If you are a business that is eligible and interested in participating in the Shop Lake Grove campaign, please complete this survey to sign up!

More Information

For more information about schedule and work hours, click here.

You can also email info@boonesferryproject.org, call 503-697-6573 and follow the city on social media with #boonesferryproject and #followthebluecones.

 

Riccardo’s Ristorante & Cafe Marzocca

This month’s Who’s Who on Boones Ferry Road features Riccardo’s Ristorante and Café Marzocca!

If you’ve lived, worked or visited in Lake Oswego in the last forty years, chances are you’ve been to Riccardo’s Ristorante or Café Marzocca on Boones Ferry Road. Opened in 1980, Riccardo’s is a warm, family, Italian restaurant where patrons are treated more like family members than customers.

Owners Georgette and Riccardo Spaccarelli are often there to greet you with a friendly smile, wonderful hospitality, and even a hug. Having a long passion for family and the Italian dining tradition – where dining is not just about eating, but more about an event – Riccardo and Georgette have created their own little part of Italy right here in the Lake Oswego community.

The Spaccarelli’s stay true to their Italian culture and cuisine – trying to turn your stomach into an Italian by using family recipes from Italy, serving only Italian wines and “the best” Italian coffee (Illy). In the warmer and drier months, they open their outdoor seating area with a large terra-cotta patio and fountains in the center for all to enjoy.

Generations of customers have gone through their restaurant over 40 years – some of the children that used to play in their fountain are now working there!

In 1990, Georgette and Riccardo decided to expand their exclusively Italian offerings by opening a café and retail wine shop – Café Marzocca and Vin Italy – located across the parking lot from Riccardo’s. In the Café, on the second Saturday of every month from noon to 3 p.m. they host a wine tasting of 6-8 wines, along with anti pasti from the ristorante.

Riccardo and Georgette were intrinsically involved in the development of the improvements for the Boones Ferry Road project. Riccardo was a key member of the eight-member project advisory committee, providing input into streetscape features, lighting, crosswalks, and interpretive elements. He recalls how the project was a dream 20 years ago – it’s been a long road to get it to the point of construction, but they are excited to start seeing some of the pieces coming together.

In conjunction with the road construction, the Spacarelli’s thought it was a good time to also give Vin Italy and Café Marzocca a facelift. New windows, doors, stonework, stucco and an awning are being placed, and Riccardo’s will also receive some architectural work once the road project is complete.

Both Café Marzocca and Riccardo’s Ristorante are participating in our monthly Shop Lake Grove raffle, so be sure to drop off an entry card when you stop by to visit!

Riccardo’s Ristorante
16035 Boones Ferry Road
(503) 636 4104
https://www.riccardoslo.com/

Café Marzocca & Vin Italy
16045 Boones Ferry Road
https://www.riccardoslo.com/cafe-bar-marzocca

Inspiring Future Civil Engineers and Construction Contractors

On Tuesday, March 3, our all-female City project team leading the Boones Ferry Road (BFR) Project engaged 20 students from Lakeridge Middle School in an all-day event to showcase the multi-million dollar road project, and to provide an opportunity to both create and observe engineering and construction in action.

Leading the way

The City project team (Crystal Shum, project lead; Stacy Bluhm, project engineer; and Katy Kerklaan, communications and public outreach), also joined by Erica Rooney, city engineer, and Chad Maxwell, construction manager from Otak, Inc. kicked off the day by sharing their unique stories and backgrounds, personal challenges or obstacles they had overcome, and how they got to where they are today in their careers.

Rene Miller, construction assistant, and Dan Payne, superintendent from Wildish – the General Contractor building the BFR project – were also on-hand to share information, fun giveaways and support the kids.

Building a road

To provide the kids with a hands-on experience, the project team and Cheri Davidson (TAG Coordinator at Lakeridge) developed a small group activity with defined roles to “Build a Road” based on engineering specifications and plan sheets that resembled similar infrastructure and elements that are being installed as part of the BFR project.

The team provided materials for the kids to purchase, and a tracking sheet for each group to manage their costs. Elements included installing: stormwater access holes, storm pipe, conduit for underground utilities, new sidewalk, new roadway with rock and asphalt, lane striping and the option to install bike lanes.

The group learned there are a myriad of skills involved in engineering and construction – not just math and science – but a lot more problem solving, project management, and working together as a team to resolve issues.

All aboard the excavator

In the afternoon, the project team led the group out in the field to show them some of the real-life issues they deal with, and had them learn from our contractors about how they operate equipment and actually construct the project.

One of the subcontractors for the project – Turney Excavating Inc. – set up stations and the kids learned about some of the technology they use (GPS) in the field and how they operate different pieces of equipment. All the kids climbed aboard a loader and excavator, looked inside 48“ stormwater pipe and access holes, viewed the new sidewalks being formed, new asphalt placed, special artistic elements, and retaining walls that were in different stages of being constructed.

This was not only memorable and rewarding for the kids, but also for the project team, consultants and contractors who participated in the day. We hope it made a difference in the kids’ lives and their career choices!

National Women in Construction Week

This special event was also timely, as it is National Women in Construction Week (March 1-7)! There is still a large gender gap in the civil engineering and construction fields.

We celebrate the wonderful women who work in construction, public works and engineering services in Lake Oswego! You are paving the way for the future.

We are proud of our all-female project team leading the BFR project to success, and inspiring other women and young girls to work in Engineering and Construction! Thanks Katy, Crystal and Stacy! (pictured below)

 

 

 

Construction Update 2/7/20

Another milestone was met this week when crews poured the first portion of new sidewalks and driveway aprons between Madrona Street and Firwood Road!

Additional concrete pours are scheduled over the coming month. Thank you to property owners and businesses for your cooperation and patience during the concrete pours.

Weather permitting, early next week crews plan to place some temporary hot asphalt down and also add some additional temporary striping within the project area travel lanes (including some side streets).

In mid-late February, crews also plan to begin paving a first base layer of asphalt on the west side of Boones Ferry Road between West Sunset Blvd. and Firwood Road., a portion of Bryant Road and a portion of Firwood Road.  At this time, they may also install the new asphalt pathway on Lanewood Street (between First Citizens Bank and Boones Way). This work is weather dependent.

A final overlay of asphalt and permanent striping will be installed at the end of the project.

Walls

Crews continue to pour new retaining walls throughout the corridor. Stone masons have been placing stone veneer on new walls at Madrona Street and in front of the Olson Memorial Clinic. This work will continue over the next few months.

Utility Undergrounding

Crews continue installing underground conduit and utility vaults between Quarry Road and Oakridge Road. NW Natural has been installing a new gas line, and electrical crews have been installing electrical conduit for street lighting and signal power. Work will continue ramping up in this area over the coming months.

PGE is expected to arrive in late February to begin their switch from overhead to underground power in the area south of Quarry Road. They will switch over services, and eventually remove the above ground power poles between Bryant and Madrona (the first segment). Some of this work is taking place during the day, and some at night. Any planned shutdowns for customers will be coordinated by the utility companies, and typically occur after business hours.

Stormwater Lines

Crews have made good progress on installing a new stormwater line on Reese Road and Boones Ferry Road. This work is being conducted at night with flaggers, to minimize impacts to traffic. Stormwater work is expected to continue over the next few weeks before crews switch to installing a new waterline.

New Stop Sign at Madrona Street x Waluga Drive

This week, a new all-way stop was installed at the intersection of Madrona and Waluga. Curb extensions have also been installed here to help with traffic calming. Watch for this new traffic pattern.

Who’s Who on Boones Ferry Road

This month’s Who’s Who on Boones Ferry Road features Naomi’s Lampshades and Lamps!

Not many businesses can say they have operated in Lake Oswego since 1942, but Naomi’s is one of those rare treasures! They are a local, independently owned, full-service lamp and lampshade store (the biggest on the west coast).

Watch the video featuring owners Celina and Mark Williams sharing their story and love for making custom lamps and repairing them. There is a running joke among Naomi’s customers that if Naomi’s cannot fix it, nobody can! So come on by, bring in your old lampshade for a refresh, or see if they can make something special incorporating a sentimental item from your childhood or a unique keepsake. They may even turn you into a lamp!

Shop Lake Grove Raffle Continues!

Our Shop Lake Grove monthly raffle continues! Each month, we are giving away TWO $100 gift cards to participating businesses located in the project area. Stop by one of these businesses to enter the raffle. Each month the raffle starts fresh, so keep coming back to visit your local businesses to enter.

If you are a business that is eligible and interested in participating in the Shop Lake Grove campaign, please complete this survey to sign up!

More Information

For more information about schedule and work hours, click here.

You can also email info@boonesferryproject.org, call 503-697-6573 and follow the city on social media with #boonesferryproject and #followthebluecones.

Naomi’s Lampshades and Lamps

This month’s Who’s Who on Boones Ferry Road features Naomi’s Lampshades and Lamps!

Established in 1942 in Lake Oswego, Naomi’s Lampshades and Lamps is a local, independently owned, full-service lamp and lampshade store, providing one-of-a-kind high-quality lamps and accessories. With over 8,000 lampshades available – and all American made – Naomi’s is the biggest lampshade supplier on the west coast. They also provide expert lamp repair and restoration, parts and accessories for all your lamp products (including the largest supply of finials), and custom lampshade and lamp design – often incorporating sentimental parts supplied by customers.

Naomi’s owners, Celina and Mark Williams, have operated the business for seven years, following from three previous owners who all retired at the store over its 77 year operation. They feel fortunate to operate a business that has been in the community for such a long time, having served multiple generations of Lake Oswego and Oregon residents.

Mark and Celina Williams have owned and operated Naomi’s for seven years

Celina has a special love for design. She particularly enjoys making her customers’ dream projects a reality. A fan of fixing anything and everything, Mark enjoys repairing lamps (and often other items!), but also making new and unique products. There is a running joke among Naomi’s customers that if Naomi’s cannot fix it, no one can.

Naomi’s staff have made some quirky and unique projects in their time, including incorporating baby shoes, glass cups, and shotguns or even making an Adam’s Family themed lamp for a Halloween party. One of their most spectacular projects was fixing and restoring the Swarovski crystal candelabras and lighting for the Arlene Schnitzer Concert Hall in downtown Portland. Mark’s most memorable repair was restoring a chandelier to its original shape and beauty that was damaged during Hurricane Katrina.

Celina and Mark are looking forward to the new, fresh look the Boones Ferry Road project will bring to Lake Grove and to serving the new residents moving to the community.

At Naomi’s, they say that if you stand in the store long enough, they can turn you into a lamp! So come on by, bring in your old lampshade for a refresh, or see if they can make something special incorporating a sentimental item from your childhood or a unique keepsake! The friendly staff at Naomi’s are here to help make your dream project a reality!

They are also participating in our monthly Shop Lake Grove raffle, so be sure to drop off an entry card in the box.

Naomi’s Lamps and Lampshades
15942 Boones Ferry Road
503-636-1884
http://naomislampshadesandlamps.com/

Construction Update 12/20/19

New Traffic Shift

In late November, the new temporary lane configuration on Boones Ferry Road of one lane in each direction and a center turn lane was extended to Oakridge Road (at the post office). Boones Ferry Road and all businesses remain open, but please plan extra travel time through the area and travel cautiously. Thank you for your patience as the traveling public gets used to this new traffic shift.

Concrete Pours and Mason Work

The project met its first major concrete milestone this week, when new concrete curbs were formed and poured on the west side of Boones Ferry Road, between Madrona Street and Firwood Road. Sidewalks, curb ramps and driveway aprons will follow over the next month.

During the concrete pours, we will notify property owners and businesses ahead of time of any temporary driveway closures or access coordination efforts. Thank you for your cooperation and patience!

Earlier this week, the mason workers arrived to begin placing stone veneer on the new walls! Pictured below, masons started forming the pattern on the wall at the corner of Madrona and Boones Ferry.

The featured photo above shows concrete being poured last night for the remainder of the retaining wall at the corner of Bryant and Boones Ferry (Bank of America).

Temporary Signal

Also last night, crews coordinated with Clackamas County to install and activate a new temporary signal at Oakridge/Reese/Boones Ferry intersection. The existing signal heads and mast arms were removed. The poles will soon follow, making room for the joint underground utility trench.

Multiple Crews

There is active work and multiple crews operating throughout the entire corridor. With the work zone expansion north of Quarry Road, crews are continuing to progress with the utility undergrounding operation. Conduit and vaults are being installed on the west side of the road, heading towards Oakridge Road. This work is being conducted at night with flagged traffic.

Some utility companies (Comcast, Centurylink) have started pulling their lines through the newly installed conduit and configuring their vaults in the area south of Quarry Road. This will continue over the coming months. PGE is expected to arrive for their switchover in the first quarter of 2020, switching over services, and eventually removing the above ground power poles. Some of this work is taking place during the day, and some at night. Any planned shutdowns for customers will be coordinated by the utility companies, and typically occur after business hours.

With the work zone expansion and lane shift north of Quarry Road, this has allowed crews to clear and remove landscaping, saw-cut the asphalt and prepare for the illumination and gas line work on the east side, which will continue over the coming month or so.

Stormwater Lines

Crews have recently been installing a storm manhole and storm line across Madrona near the intersection of Boones Ferry. During this work, expect flagged traffic on Madrona.

In early January, crews plan to start working on installing a new stormwater line on Reese Road, near Lake Grove Avenue, working towards Boones Ferry, then progress south of Reese Road on Boones Ferry towards Bryant Road. This work will be conducted at night, with lane closures and flaggers.

Quarry Road Radar Sign– December 30

Crews need to configure some equipment on the newly installed speed radar feedback sign on Quarry Road. This is planned for Monday, 12/30 from 9 a.m. – 4 p.m. Lane closures will be in place and traffic will be flagged.

Who’s Who on Boones Ferry Road

This month’s Who’s Who on Boones Ferry Road features Healthy Pet!

Watch the video to hear why they love Lake Oswego customers!

Healthy Pet is a local, independently owned, holistic pet supply store that has been in business – on Boones Ferry Road – since 1986! They specialize in providing premium foods and high quality products that you may not find at the bigger box stores. Women owned and operated, Healthy Pet prides themselves on having passionate, knowledgeable, friendly, and long-standing staff members who are here to help provide solutions and give advice (with a side of therapy!) to customers and their pets.

The Holidays are a special time of the year at Healthy Pet! Stop by to check out their cute toys, apparel and holiday treats! They are also participating in our monthly raffle, so be sure to drop off an entry card in the box!

Support Your Lake Grove Businesses During the Holiday Season!

Boones Ferry Road and all its businesses remain open during construction. This holiday season, please come out and support your friends and community businesses that make Lake Oswego a great place to live, work and play! Follow the blue cones and signs to access business driveways in the work zones, and please plan some extra travel time.

Throughout the holiday season, the project team have released a series of short holiday-themed videos with catchy music, featuring project area businesses. Check them out on the City’s social media accounts, or click on the links below!

Enter the Shop Lake Grove Raffle

Our Shop Lake Grove monthly raffle continues! Our latest raffle winner is local resident Nancy Headley, pictured below with Papa Murphy’s employee Maria Sandobal, collecting her pizzas!

Each month, we are giving away TWO $100 gift cards to participating businesses located in the project area. Stop by one of these businesses to enter the raffle. Each month the raffle starts fresh, so keep coming back to visit your local businesses to enter.

If you are a business that is eligible and interested in participating in the Shop Lake Grove campaign, please complete this survey to sign up!

More Information

During the Christmas and New Year weeks, there will be some small skeleton crews working, but no work is planned for 12/24, 12/25 or 1/1.

For more information about schedule and work hours, click here.

You can also email info@boonesferryproject.org, call 503-697-6573 and follow the city on social media with #boonesferryproject and #followthebluecones.

Urgent Paving Work Today at Boones Ferry/Bryant/Firwood Intersection

Starting today, Tuesday December 17, at approximately 10 a.m., the Boones Ferry/Bryant/Firwood signal will be put into all-way flash in order to pave portions of the intersection. Flaggers will be stationed at the intersection to help control traffic. This work is expected to take up to two hours.

Crews have been unable to receive ‘hotmix’ asphalt at night, but were able to secure a delivery this morning while the weather allows. The pavement needs to be improved before the next big rainfall occurs (later this week).

Please expect some temporary delays and plan extra travel time during this work. We appreciate your understanding and patience in this urgent matter.

Healthy Pet

This month’s Who’s Who on Boones Ferry Road features Healthy Pet!

Healthy Pet is a local, independently owned, holistic pet supply store that has been in business – on Boones Ferry Road – since 1986! They specialize in providing premium foods and high quality products that you may not find at the bigger box stores. Women owned and operated, Healthy Pet prides themselves on having passionate, knowledgeable, friendly, and long-standing staff members who are here to help provide solutions and give advice (with a side of therapy!) to customers and their pets.

Brittany, Kate, Andie and Snickers

Kate Bisturis, one of the managers at Healthy Pet, has worked there for 13 years. She grew up in Lake Oswego, attended Lakeridge High, and Healthy Pet was her first full time employer. Kate is proud she has been part of the Healthy Pet family for so long, seeing it grow and develop as an independent, small business in the community of Lake Oswego.

Healthy Pet loves supporting the people and pets of Lake Oswego. They particularly appreciate their incredible customers who are willing to go above and beyond for their personal pets, but also their store pets.

Tofu, Healthy Pet’s store cat!

Tofu is their latest store kitty, and she has a special story. She came to Healthy Pet from a shelter in Chehalis, Washington. She was 14 and had hyperthyroidism. Within a month of getting her, their incredible customers came together to raise enough money to have a special radioactive iodine treatment to help her. Thanks to the community, she is now doing fabulously and continues to enjoy ruling over the store and spreading kitty love to all!

So far during construction, Healthy Pet has appreciated having the blue signage to designate where business driveways are to help customers continue to access their store. Having been located right on the corner of Boones Ferry Road and Bryant for more than 30 years, they have seen how congested that intersection can get, and at times, daunting. They are looking forward to having that intersection improved for the safety and access of the traveling public.

The Holidays are a special time of the year at Healthy Pet! Stop by to check out their cute toys, apparel and holiday treats! They are also participating in our monthly raffle, so be sure to drop off an entry card in the box!

Healthy Pet
16140 Boones Ferry Road, Lake Oswego
503-636-3186
https://www.healthypetlakeoswego.com/

Emergency Sewer Repair at Boones Ferry/Firwood/Bryant Road Intersection

Crews have discovered a broken sewer line at the Boones Ferry/Bryant/Firwood Road intersection. Public Works crews are on site, coordinating and preparing with the Boones Ferry Road project crews to conduct an emergency repair of the line. In preparation for the repair, Public Works crews are currently cleaning out the sewer line on Firwood Road, near Albertson’s and the Shell station. During this time, traffic is flagged on Firwood Road between Boones Ferry Road and Waluga Drive.

Starting at 8 p.m. tonight through 6 a.m., the Boones Ferry/Bryant/Firwood Road traffic signal will be shut off and traffic will be flagged at the intersection to accommodate the emergency repair.

Please expect significant delays during this repair, and avoid the area if possible. We apologize for this unanticipated inconvenience, and thank you for your patience while crews work to repair the line.

Construction Update 11/19/19

New Traffic Shift – Scheduled for Thursday Night 11/21

Weather permitting, starting Thursday night 11/21, the work zone is expected to expand further north. The temporary traffic configuration on Boones Ferry Road from W. Sunset Drive to Bryant Road, will be extended to Reese Road (at the post office).

Some existing striping will be removed and new temporary striping placed. Instead of four lanes there will be three: one lane in each direction, plus a center turn lane. Traffic will be shifted to the west side of the road while crews work on the east side.

This traffic change will give crews room to maneuver and still keep the road open, but at times there will be flaggers and brief delays with equipment.

Click here to watch a video about this upcoming traffic change.

To implement this traffic shift, crews will work at night from 10 p.m. – 6 a.m. The signal at Bryant/Boones Ferry will be shut down and traffic will be flagged. Please expect delays and obey flaggers’ directions.

Once this new work zone is set up on Boones Ferry Road between Bryant and Reese Road, crews will begin installing a new gas line, illumination conduit, water line and stormwater line on the east side (Healthy Pet/Car Wash side).

Mid-morning Lane Closure 11/22 – Bryant Road at Sunset Drive

On Friday, 11/22, Lake Oswego Public Works Sewer Crews will be televising and cleaning out an access hole and sewer line at the intersection of Bryant Road and Sunset Drive. This work is expected to take place from 9:30 a.m. – 12 p.m. During this time, Bryant Road will be reduced to one lane and traffic will be flagged. Please expect some delays and plan extra travel time. If you have any questions about this work, please contact Public Works on 503-635-0280.

Who’s Who on Boones Ferry Road

This month’s Who’s Who on Boones Ferry Road features Zupan’s Markets! Watch the video to hear why they love Lake Oswego customers!

The holiday season is the busiest time of the year for Zupan’s, and right now they are offering their specialty Thanksgiving Dinner – above and beyond what you would usually find at a traditional store. Zupan’s offers the complete Thanksgiving meal for $199! Click here for more information.

Stop by to visit Zupan’s to check out their incredible array of seasonal products, holiday decorations and locally sourced items!

They are also participating in our monthly raffle, so be sure to visit the bakery/cafe and drop off an entry card in the box!

Support Your Lake Grove Businesses During the Holiday Season!

Boones Ferry Road and all its businesses remain open during construction. This holiday season, please come out and support your friends and community businesses that make Lake Oswego a great place to live, work and play! Follow the blue cones and signs to access business driveways in the work zones.

Enter the Shop Lake Grove Raffle

Our Shop Lake Grove monthly raffle continues! Each month, we are giving away TWO $100 gift cards to participating businesses located in the project area. Stop by one of these businesses to enter the raffle. Each month the raffle starts fresh, so keep coming back to visit your local businesses to enter.

If you are a business that is eligible and interested in participating in the Shop Lake Grove campaign, please complete this survey to sign up!

More Information?

There is no work scheduled to take place on the project from Wednesday night 11/20 through Sunday night 12/1. Crews are expected to return after the Thanksgiving holiday weekend, on Monday, 12/2.

For more information about schedule and work hours, click here.

You can also email info@boonesferryproject.org, call 503-697-6573 and follow the city on social media with #boonesferryproject and #followthebluecones.

Coming your way: a safer, more appealing Boones Ferry Road for all