Permit Expiration
Your permit is valid for 180 days from the date of issuance or from the date of the most recently approved inspection.
-
As long as you are continuing to work on your project and calling for regular inspections, your permit stays active.
-
Your permit expires if work is suspended or abandon for 180 days or more.
-
If you can't work within a 180-day period and don't wish to abandon the project, you may submit a written request to extend your permit additional 180-day period.
-
Once you have received your final building inspection approval, your permit is finale and occupancy is allowed.
Please contact the Building Department for more information.
503-635-0290