2026 Pavement Rehabilitation
Paving is expected to take place on several streets in Lake Oswego in late spring/summer 2026. Paving activities may include extensive repair areas, grinding existing pavement, a new overlay or pavement of the driving lanes, new curb ramps, signal improvements (radar vs loops), storm drains, and some waterline upgrades.
The following streets are planned for this summer’s paving project:
- Kruse Way, from Bangy Road to Daniel Way,
- Bangy Road, from south of Kruse Way to Burma Road,
- Kruse Oaks Drive, from Kruse Way to Meadows Road,
- Hallmark Drive, from Mercantile Drive to Douglas Way,
- Collins Way, from Hallmark Drive to Boones Ferry Road, and
- Douglas Way, from Hallmark Drive to Boones Ferry Road.
Other work also includes:
- Major upgrades to the existing signalization detection at 5 intersections:
- Kruse Way and Carman Drive,
- Kruse Way and Westlake Drive,
- Kruse Way and Kruse Oaks Drive,
- Bangy Road and Meadows Road, and
- Bangy Road and Bonita Road.
- 60 new Americans with Disabilities Act (ADA) curb ramps, 44 mostly located at the intersections with the paving limits, and 16 located in other areas of the city that were identified as high priority under the ADA Transition Plan.
- About 200 ft of new waterline on Hallmark Drive, between Collins Way and Mercantile Drive.
Below is a map of the streets being paved in 2026:
Schedule and Phasing
Curb ramps, signal detection improvements, and waterline work is expected to be taking place in the first phase of construction in June or July. Phase two includes major paving, striping, and restoration work.
Most of phase one activities will take place during the day from 7 am- 6 pm, Monday to Friday. Lane closures and sidewalk closures will be in place, especially for the curb ramps, signals, waterline, and storm drain work.
Major asphalt grinding and paving work is expected to take place in July/August/September. To minimize traffic and business impacts, nighttime paving will take place on Kruse Way, Bangy Road, Kruse Oaks Drive, and Douglas Way from 8 pm- 6 am. Hallmark Drive and Collins Way are expected to be paved during daytime hours, 7 am- 6 pm. Expect delays and plan extra travel time. Lane closures and shifting traffic will be in place.
Project Updates
April 2026
The project is currently out to bid for a general contractor. A contractor is expected to be hired in mid-May, with construction starting in late-May or early June.
More details on schedule will be shared once a contractor is hired.
Dan Payne
Construction Inspector/Project Manager
503-635-0261