Fosberg Road Drainage Improvements

Fosberg Road is a mostly uncurbed street where, during periods of heavy rain, the section south of Glacier Lily Street experiences severe shoulder erosion and the flooding of private properties.  This project will construct the necessary infrastructure to capture the runoff and manage it within the City's stormwater system.  The project, to be constructed between Carmen Drive and Glacier Lily Street, is expected to extend the existing curb up the westerly side of the road to the area of Glacier Lily Street.  The project will also include new storm pipe and inlets along the lower segment of Fosberg Road.  Additionally, the existing storm inlets at Glacier Lily will be replaced with new inlets that are more efficient at capturing the runoff that flows out of the neighborhood to the east.

This past summer (2021), several private utility companies relocated their underground facilities in advance of the storm work.   The contract for the storm construction has been awarded and the contractor is set to begin the pipe and curb work in mid-October.  Construction will continue through the winter and is scheduled to be completed in the spring of 2022.  Following the completion of the storm and curb improvements, during the summer of 2022, the City pavement program will repave the length of Fosberg  from Carmen Drive to Melrose Street.

Project Updates: 

Construction Phase is well underway!  Please follow construction signs and watch out for flaggers, crews, equipment and steel sheet in the roadway. 

September/October 2021:

Contractor mobilizes crew, materials and equipment on Fosberg Road project site and staging site between Parkview Drive and Melrose Street. Tree protection fencing and Erosion control measures installed.

October/November 2021:

Contractors being installing new 18” corrugated plastic pipe underground along West side of Fosberg between Parkview and Glacier Lilly.  Temporary paving trench at the end of each week.

December 2021:

Pipe installation continues. Fosberg Road will be closed to through traffic 12/20-12/31, during 8 a.m. - 4 p.m., to complete the pipe installation across Fosberg Road and connection point to Glacier Lilly. Local access only will be given to residents along Fosberg west side.  Please follow detour signs or find alternative routes.  Road will be open at end of each day shift. 

January 2022: 

Pipe installation continues. Fosberg Road will be closed to through traffic from early January through mid-January, Monday to Friday 8 a.m. - 4 p.m., to complete the pipe installation across Fosberg Road and connection point to Glacier Lilly. Local access will be given to residents along Fosberg west side.  Please follow detour signs or find alternative routes.  Road will be open at end of each day shift. 

 

Fosberg Road Construction
Fosberg Road
Project Details
ID: 
WO 288
Year: 
2020
Status: 
Active
Project Contact: 

Rob Amsberry, Project Manager

email

Construction Line 503.635.0261

Attachments