Lake Oswego Interceptor Sewer Inspection

The City is performing a routine underwater inspection of the Lake Oswego Interceptor Sewer beginning after Labor Day weekend and continuing through Winter 2021/22. This work will help make sure the buoyant sewer pipeline that lies across Oswego Lake continues to serve the community reliably.

The City will be using barges to deploy divers and robotic cameras to inspect each segment of the pipeline. Boaters are asked to respect the 200-foot no-wake safety zone where work is occurring.

Frequently Asked Questions 

What is the Lake Oswego Interceptor Sewer?

The Lake Oswego Interceptor Sewer is a 42-inch buoyant pipeline that lies across Oswego Lake. The pipeline was built in 2011 to replace the City’s aging in-water sewers and provide service for central and western portions of Lake Oswego.

Why is the inspection needed? Why now?

The City is performing a planned ten-year inspection of the pipeline – the first since the pipeline was constructed. This checkup will help the City identify any repairs or maintenance needed to keep the pipeline in good condition.

How long will the inspection take?

The inspection project will begin after Labor Day weekend and is planned to be completed in Winter 2021/22. The City scheduled the work when the least disruption to lake activities will occur.

What’s involved in the inspection?

The City has a team of underwater divers along with robotic cameras and sonar equipment to thoroughly assess each segment of the pipeline interior and exterior, and the wave action tethers and anchors that keep the buoyant pipeline in place.

What will I notice?

You may notice barges on the lake and equipment where divers are inspecting the sewer pipeline to identify repair or maintenance needs. Work hours will be Monday through Friday between 7am and 6pm. Occasional noise from generators and other equipment may be heard from the barges during work hours.

Where is the inspection work happening?

Diving and other inspection activities will be happening continuously throughout the lake. The main work area will be near the barges, which will deploy from the Lake Oswego Corporation marina. Once in the water, the barges are expected to follow the path of the sewer pipeline moving generally west to east as workers complete inspection of each pipeline segment.

How can I stay up to date?

The project webpage will be updated regularly with information about where barge inspection activities are occurring. We’re working closely with Lake Oswego Corporation to keep mariners and lake-shore residents informed. We’ll also share periodic progress updates through the City’s social media channels and e-newsletter.

What will the City do with the inspection results?

The City will use the findings from the inspection work to make good data-driven decisions about any upgrades, repairs, or ongoing maintenance activities needed to make sure the sewer pipeline continues to serve our community reliably.

Project Updates: 

September 16, 2021 Update 

What’s happening:

The week of Sept. 20th, the City will be loading equipment onto barges on Oswego Lake from Allen Road to prepare for the inspection work.

When: Mon-Fri 7am-6pm

Where: 

 

September 9, 2021 Update 

What’s happening:

The week of Sept. 13th, the City will finish moving barges into the water using the Lake Oswego Corporation marina. Ramp time at the marina will be limited during this time.

Once in the water, the barges will move to the western end of the lake where equipment will be loaded from Allen Road before inspection of the first segment of sewer pipeline begins.

When: Mon-Fri 7am-6pm

Where: 

August 25, 2021 Update 

What’s happening:

The week of Sept. 7th, the City will be moving barges into the water using the Lake Oswego Corporation marina. Ramp time at the marina will be limited for about three days.

Once in the water, the barges will move to the western end of the lake where equipment will be loaded from Allen Road before inspection of the first segment of sewer pipeline begins.

When: Mon-Fri 7am-6pm

Where: 

 
Project Details
ID: 
WO 317
Year: 
2021
Status: 
Active
Project Contact: 

James Ellis, Senior Engineeering Associate

503.635.0261

Email