State Street Sewer Project

The City’s 2013 Wastewater Master Plan (WWMP) identified the Lakewood Sewer Trunk Rehabilitation (located on State Street) as one of several pipeline repair projects. The wastewater mainline was identified as having less than 10 years of remaining useful life. Staff was hopeful the issues could be addressed via pipe-lining in order to minimize costs and impact. However, once the design phase started, the pipe was found to have several significant sags, or low spots, which can lead to blockages and overflows. These sags can only be corrected through open excavation and replacement of the pipeline.

This project will replace the sewer pipeline restoring useful life, reducing risk of overflows, and minimizing infiltration and inflow (I/I) into the City’s sewer system.

The project limits are along State Street/Hwy 43 from North Shore Road to just north of Foothills Road. The scope of work includes:

  • installing approximately 850 linear feet of new sewer mainline
  • installing seven new manholes
  • restoring the disturbed area (asphalt, pavement markings, landscaping, etc.)

Schedule 

Construction is expected to begin in early June and continue through summer 2022. To minimize impacts to the traveling public, this work will be conducted at night between 9 p.m. and 5 a.m. 

Project Updates: 

May 10, 2022

In early June, crews expect to begin installing a new major sewer pipeline on State Street between Foothills Road and Northshore Road. To minimize impacts to the traveling public, this work will be conducted at night. Key information:

  • Typical work hours are Monday to Friday between 9 p.m. and 5 a.m.
  • During work hours, lane closures will be in place and traffic will be shifted. Flaggers may direct traffic.
  • Access will remain open to businesses and emergency services at all times.
  • Night work can be noisy with saw cutting, jack hammers, rock excavation, back-up alarms, truck traffic, and other equipment.
  • Steel plates may be placed in the roadway and equipment stored on side streets.
  • Please expect delays, plan extra travel time, follow traffic signs, and watch for flaggers.

Construction is expected to take up to three months to complete. Schedules are subject to change.

Thank you for your patience and understanding during construction.

April 14, 2022

City Council awarded a public improvement construction contract to Icon Construction & Development on April 5, 2022. 

Construction is expected to start in spring 2022 and take a few months to complete. Per ODOT requirements, work will be conducted at night to minimize impacts to the traveling public. 

Schedules are subject to change. 

May 10, 2021

Wallis Engineering has been selected as the designer for this project.

March 31, 2021

The City is currently soliciting a scope and fee from consultants for this project. The City anticipates awarding the contract for construction in May of 2022.  Construction is expected to begin in summer 2022.

WO 311 Image
Project Details
ID: 
WO 311
Year: 
2022
Status: 
Active
Project Contact: 

Javier Moncada, Project Construction Manager

(503) 635-0261

Email