Second Floor Renovations!


Exciting updates are afoot at the library. From February 18th through March you will notice disruption on the upper level of the library on the north side of the building. Our reference area will be undergoing some upgrades to ensure we are in compliance with building codes and to provide a better patron experience for our visitors. 

Here's what you can expect to see/hear each week:

Project Milestones & Important Notes for the week of February 18-23

  • Conference room closed 2/19-3/11 AND 3/16-3/20 (estimated)
  • Reference shelving temporarily relocated along 2nd floor North windows
  • Temporary storage area established near Nonfiction 000s
  • Construction of new workroom wall begins, to replace cubicle wall
  • Please excuse our noise and dust!

Project Milestones & Important Notes for the week of February 24-29

  • Conference room closed 2/19-3/11 AND 3/16-3/20 (estimated)
  • Staff office furniture dismantled and temporarily stored
  • Painting in staff work areas
  • Wall construction, electrical work and doors installation
  • Please excuse our noise and dust!

Project Milestones & Important Notes for the week of March 1-8

  • Conference room closed 2/19-3/11 AND 3/16-3/20 (estimated)
  • Painting in staff work areas
  • Carpet installation in staff work areas
  • Office furniture re-installation in staff work areas
  • Please excuse our noise and dust!

Project Milestones & Important Notes for the week of March 9-15

  • Conference room closed 2/19-3/11 AND 3/16-3/20 (estimated)
  • Conference room open limited days from 3/12-3/15 (estimated)
  • Reference area collections temporarily inaccessible from 3/12-3/31 (estimated)
  • Office furniture re-installation in staff work areas
  • Please excuse our noise and dust!

Project Milestones & Important Notes for the week of March 16-22

  • Conference room closed 3/16-3/20 (estimated)
  • Conference room re-opens 3/21 (estimated)
  • Reference area collections temporarily inaccessible 3/12-3/31 (estimated)
  • Microfilm readers, privacy stations, and up-down stations temporarily inaccessible 3/16-3/31 (estimated)
  • Computer stations along short light well temporarily inaccessible 3/17-3/20 (estimated)
  • Reference area furnishings moving to temporary storage
  • Painting in public area and conference room
  • Carpeting in public area and conference room
  • Reference desk and printing equipment moving to other side of stairwell during painting and carpeting work
  • Please excuse our noise and dust!

Project Milestones & Important Notes for the week of March 23-29

  • New shelving installation
  • Select furniture pieces returning to reference area
  • Please excuse our noise and dust!

Project Milestones & Important Notes for the week of March 30-April 3

  • Reference collections coming out of storage
  • Remaining furniture pieces returning to reference area
  • Microfilm readers, privacy stations, and up-down stations coming out of storage
  • Please excuse our noise and dust!