New City Hall Project

Project Background / Summary: 

Click here to check out the proposed design!

New City Hall Project Overview

The Lake Oswego Redevelopment Agency is working on the planning and design of a new City Hall in downtown Lake Oswego. The new building, which will be constructed next door to the existing City Hall, will include new facilities for Police and 911 dispatch services, city offices, a larger emergency operations center, and retail spaces. The majority of the project is funded by urban renewal. The new building will be 3 stories over one level for secured police parking. After the construction of the new building, the existing city hall will be demolished and replaced with customer parking and plazas.

Police Facility Background

The city has studied the siting and construction of a new police facility since 2001.  The current space on the second floor of City Hall has long been recognized as inadequate for housing Police and 911 dispatch services.  The building cannot be secured, there is insufficient space for police operations, and the building does not meet current seismic standards for essential services.

Following several site studies, needs assessments, and condition analyses, in 2013 the Lake Oswego City Council, acting as the Lake Oswego Redevelopment Agency (LORA) Board, decided to purchase the three privately-held parcels immediately east of city hall as the site for a new police and 911 facility. The properties were acquired in 2015 and 2016. Following the decision to replace city hall, rather than just build a new police facility, a new city hall will be constructed on the properties next door to the existing city hall. 

City Hall Background

The existing Lake Oswego City Hall, value-engineered and constructed in 1986 for about $5 million, has multiple and significant building and programmatic deficiencies identified through several studies and condition assessments.

The inadequate drainage system of the building, compounded by the long history of excessive amounts of rainwater penetrating through the building's envelope (an EIFS cladding system), has damaged the underlying components of the building’s exterior wall. It is no longer feasible to maintain the building envelope and the lack of drainage system coupled with the significant concealed damage under the EIFS cladding removes the possibility of doing targeted repairs.  An assessment conducted in July 2015 recommended a full replacement of windows, doors, EIFS and underlining sheathing and insulation, roof, and repairs to the exterior walls. Additionally, the building's systems such as the HVAC, generator, and elevators are in need of replacement.

A seismic and structural assessment of the building noted that the structure would not perform well in an earthquake and the cost to retrofit the building would compare to the construction of a new facility. On March 21, 2017, the City Council decided to build a new City Hall with urban renewal funds rather than making the costly repairs and affirmed that decision on June 12, 2018.

 

 

Status Updates: 

Previous Updates

Please see the list of project milestones (listed under key documents) for the highlights of work on the project to-date. 

May 21, 2019 LORA meeting

At the meeting, the Board approved early work site preparation and material procurement in the amount of $8,107.796.00.  This authorization locks in construction costs for approximately 25% of the project cost, reduces wet-weather impacts and keeps the project on schedule.  The design team has completed 75% construction documents and anticipates completing 90% of this phase in early June. View the meeting materials.

April 1, 2019 DRC meeting

The DRC approved the Development and Conditional Use Permits and Design and Minor Variances to construct the new City Hall and associated parking.  View the meeting on our YouTube channel.

November 6, 2018 LORA meeting

The LORA Board approved the schematic design on Tuesday, November 6, 2018. View the meeting materials (design, floor plans, site plans).  The next steps for the project will be to hold a pre-application conference, submit the land use application, meet with the Evergreen neighborhood association, and schedule a hearing with the Development Review Commission once the application is complete. The work includes further development of the design details both on the exterior and interior of the new building.

June 12, 2018

The LORA Board directed staff to proceed with the concept to construct a new city hall on the property next to the existing city hall building. A revised concept was approved by the Board on July 17. The meeting materials are posted online.

Location
366 3rd Street
Lake Oswego, OR 97034
Project Details
ID: 
WO 260
Year: 
2015
Status: 
Active
Owner/Applicant: 
Lake Oswego Redevelopment Agency
Project Contact: 

 

Construction Hotline
503-635-0261

Sid Sin, Development Project Manager
503-697-7421

 

 

Attachments Neighborhoods

Evergreen

chevron_right