Rassekh Skatepark

Rassekh Skatepark 2023 Project Update

November 28, 2023: Here is a pictorial update on how the skatepark construction is progressing.

 

 

 

 

 

 

 

 

 

 

 

October 18, 2023: California Skatepark is mobilized on-site and continues to do fine grading in preparation for concrete.

 

 

 

 

 

The 2023 City Council Goals include an initiative to “invest in Lake Oswego’s high-quality parks, natural areas, and recreational amenities” by developing a funding strategy for Rassekh Park and constructing Phase 1, which includes the skatepark. Following this direction, Lake Oswego Parks & Recreation solicited bids to construct Phase I of the project in early June. On June 27 Lake Oswego City Council awarded a contract for the general construction of Phase I of Rassekh Park. The skatepark will be constructed concurrently but through a separate contract with California Skateparks, who also designed the project.Construction will begin in July 2023 and is expected to be complete in early summer 2024.

In addition to the skatepark, Phase I of Rassekh Park will include construction of the all public right-of-way improvements for Stafford Road (street trees, street lights, etc.); reconstruction and widening of the multi-use path along Stafford Road; construction of the new access road from Atherton Drive; a portion of the paved parking lot and a temporary gravel overflow parking area; and the restroom building. Phase I will also provide critical utilities to the site (water, stormwater, and sanitary sewer service and electricity), all of which will be needed to serve the full build-out of the park. For more information on the Rassekh Park project, click here. We are committed to completing the full build-out of Rassekh Park, and are working to develop a funding strategy to build the next phase as soon as possible.

What is this project about?

In October 2021 City Council directed Lake Oswego Parks & Recreation to develop a new 10,000-square-foot skatepark as part of Rassekh Park. This decision was based on community feedback received through the Rassekh Park design and public outreach process, as well as public testimony in support of the skatepark at City Council meetings. Lake Oswego's former skatepark was closed in 2015 to make room for the new Maintenance Building. We are very excited to be partnering with California Skateparks to design and build this new skating facility for the Lake Oswego community.

Where will the skatepark be located?

The Rassekh property is a 9.8-acre property located on Stafford Road, just northwest of the roundabout at Stafford Road and Atherton Drive. The property was originally acquired by the City in 1996 as a result of the 1990 Parks Bond, with the intention of being developed as a park with opportunities for active recreation for the community. The skatepark will be located in the northeast corner of the Rassekh Park property and will be integrated with the park's network of trails and other park elements such as the multi-sport athletic field, picnic shelter, restrooms, drinking fountains, seating, and play area. Click here to learn more about the overall design for the Rassekh Park.

     
Project Updates: 
  • September 13, 2023: Initial digging of the skatepark started. 
  • June 27, 2023: City Council awarded the construction contract for Phase I of Rassekh Park to Paul Brothers, Inc. Construction will begin this month and is expected to be complete in early summer 2024. This will start the process for California Skatepark to work with Paul Brothers on constructing the skatepark and areas around the skatepark.
  • June 20, 2023: Tree removal work was initiated at Rassekh Park in order to prepare the site for Phase I construction later this summer. Tree removal work is expected to be underway through June 30.
  • April 2023: The 2023 City Council Goals include an initiative to “Invest in Lake Oswego’s high-quality parks, natural areas, and recreational amenities” by developing a funding strategy for Rassekh Park and constructing Phase 1, which includes the skatepark. Following this direction, Lake Oswego Parks & Recreation is moving forward with soliciting bids to construct the first phase of the project. Phase 1 will include the skatepark, public restrooms, a new access road, and a portion of the parking lot. In addition, Phase 1 will set the stage for future development by constructing the public right-of-way improvements and the backbone for the utilities that are required to support the full build-out of the park. The multi-sports athletic field, play area, walking trails, covered picnic area, and maintenance building will be constructed in a future phase. Bid information will be presented to Council in May.
  • December 2022: Bids were opened in November 2022; however the bids came in significantly higher than expected. On December 20 the City Council voted to postpone the Rassekh Park project until a funding strategy is developed.
  • September 2022: Bid documents are being prepared and the release date for the Request for Bids is October 11. 
  • August 2022: The land use application was approved at the Development Review Commission meeting on July 18 and findings were approved on August 1.
  • May 2022: The design process is now complete. Thank you to all who participated!
Development Review Type: 
Development Review Commission
Development Review Status: 
Approved
Location
18011 Stafford Road
Lake Oswego, OR 97034
Project Details
Year: 
2021
Status: 
Active
Project Contact: 

Kyra Haggart
Park Analyst / Project Manager
Lake Oswego Parks & Recreation
P.O. Box 369
Lake Oswego, OR 97034

Phone: 503-697-6576
Email: khaggart@ci.oswego.or.us

Hearing Date: 
Wednesday, July 6, 2022
Related Meetings Related Links Related Projects Attachments Neighborhoods

Palisades

chevron_right