New City Hall Project
The new City Hall is located at the corner of A Avenue and 3rd Street in downtown Lake Oswego. At 73,000 square feet, the new City Hall provides a seismically safe, energy efficient and better functioning building for the community and City staff.
New City Hall - Open
City departments have moved into the new City Hall. The moves signal the end of Phase 1 of the project and the beginning of Phase 2, demolition of the old City Hall and construction of the upper parking lot and civic plaza.
The new City Hall opened to the public on April 19, 2021. There are two main entrances:
- The A Avenue entrance on the north end of the building has parking on A Avenue.
- The south entrance can be accessed through City Hall’s existing lower parking lot from 4th Street.
View map for building access and road closures.
What's in the New City Hall
- Police Department (1st Floor)
- Information Technology (1st Floor)
- Building Department (2nd Floor)
- Engineering Department (2nd Floor)
- Planning Department (2nd Floor)
- Public Information Office (2nd Floor)
- Arts Council (2nd Floor)
- Booktique (2nd Floor)
- City Manager’s Office (3rd Floor)
- City Attorney’s Office (3rd Floor)
- Council Chamber / Court Room (3rd Floor)
- Finance Department (3rd Floor)
- Human Resources (3rd Floor)
- Municipal Court (3rd Floor)
- Redevelopment Agency (3rd Floor)
- Sustainability (3rd Floor)
Phase 2 - Demolition & Construction
Phase 2 consists of demolition of the existing City Hall and construction of a new civic plaza, surface parking, and street improvements.
Parking
During Phase 2 construction, there will be very limited parking - both at City Hall and on-street. To minimize any impacts to abutting neighbors, the City encourages the use of the City’s public parking lots in the downtown area along State Street or at First Street and B Avenue.
What you should know
- A mentioned, parking will be limited. Parking in the lower lot off of 4th Street will be available.
- The north half of the northbound lane on 4th Street between A Ave and Evergreen will be closed during Phase 2. The southbound lane will remain open.
- Access to neighboring buildings or existing private parking will generally not be impacted. Although, there may be occasions where 4th Street may be closed for short periods of time for construction activities.
- Building demolition began the week of April 5 and will last about four-six weeks.
- During demolition work hours, people can expect an increase in noise and truck traffic.
- Construction will typically occur 7 a.m. to 6 p.m. Monday through Friday and on Saturday on an as-needed basis. Construction times may be extended for special project needs.
Once building demolition is complete, work will begin for the new civic plaza, surface parking, and street improvements.
Throughout demolition/construction, the project site will be an active construction zone. Please do not enter or disturb the fencing.
Phase 2 is anticipated to be completed by the end of August. The official building opening with ribbon cutting event is tentatively scheduled for September.
Note: The project team strives to make the weekly construction update as accurate as possible, however, all work and road closures are subject to change depending on unforeseen conditions. Crews may occasionally work on Saturdays.
2021
- March - Move into new City Hall
- April - Begin demolition of existing City Hall, begin civic plaza and surface parking construction
- September - Project Completed
Weekly Project Schedule:
Aug 16 -21
- Basalt stone veneer installation continues.
- Site flatwork forming and pouring continues.
- Final grading upper and lower parking lots.
- Upper parking lot paving on 8/20
- 4th St. & A Ave. Grind & Inlay on 8/20.
- Lower parking lot entrance apron demo and replacement.
- Lower parking lot enclosure panels completes.
- Landscaping installation continues.
- Final stair pour at North end of site.
- Trash enclosure plumbing & electrical connections.
- Bike Shelter wood ceiling installation.
Aug 9 -14
Note: The east-bound south lane of A Avenue and the south intersection of A Ave. and 3rd St. will be closed from 8/11 through 8/21 for the crosswalk and grind & inlay activities. The lane and intersection closure will be 24 hours, 7 days a week until the work is complete.
- Miscellaneous site footings form and pour.
- Basalt stone veneer installation continues.
- Site flatwork forming and pouring continues.
- Light pole erection.
- Retaining wall guardrails installation completes.
- Metal panel and roofing begins on Trash and transformer enclosures and bike shelter.
- Curb & gutter forming and placement.
- 3rd St. & A Ave. intersection
- Demo & grading for crosswalk / impact slabs
- Form & pour crosswalk and impact slabs.
July 26 -31
- SW Retaining wall pour and stripping.
- Retaining wall backfill completes.
- Miscellaneous site footings form and pour.
- Basalt stone veneer installation begins.
- Site flatwork forming and pouring continues.
- Trash enclosure, bike shelter, and transformer enclosure steel begins.
- Thursday, 7/29:
- Viking Sprinkler will be onsite to modify the lines at the east upper window in the council chambers. This work is anticipated to take about 4 hours and should be minimally invasive.
- JH Kelly & Team Electric/Pacific Power will be onsite at 0300 to reroute the fuel line from the day tank to the generator. This work is anticipated to take 6-8 hours.
July 19 -24
- North end of surface parking lot closes for underground utilities installation through Friday 7/23.
- Sanitary connection to trash enclosure.
- Excavation for new catch basin and storm line continues.
- Excavation for transformer footings continues
- 4th St. curb & gutter pour.
- Planter CMU installation.
- Site flatwork forming and pouring.
- Lower parking lot utilities installation.
- Transformer enclosure footing prep and pour.
- Miscellaneous site footing prep & pour.
- Stormwater planter infill.
- SW retaining wall reinforcing and close-up.
July 12 - 17
- North end of surface parking lot closes for underground utilities installation. Through 7/23.
- Sanitary line clean-out installation.
- Sanitary connection to trash enclosure.
- Excavation for new catch basin and storm line begins.
- Pour SW retaining wall footing & CMU Alley planter.
- SW retaining wall boardform formwork begins.
- Trash enclosure slab on grade pours.
- A Ave. sidewalk forming and pours.
- 4th St. curb & gutter prep and pour.
July 5 - 10
- North end of surface parking lot closes for underground utilities installation 7/6 - 7/23.
- MH-04 in easement.
- SW retaining wall footing excavation.
- SW retaining wall footing formwork and reinforcing.
- CMU planter footing at stairs formwork begins.
- Alley entrance and A Ave. sidewalk grading and pour prep.
- Retaining wall backfilling continues.
June 29: Final paving for 3rd Street between A Ave and Evergreen Road. 3rd Street will be closed between 7am - 4pm.
June 21 - 26
- Removal of existing alley entrance and catch basin.
- Center retaining wall formwork continues.
- CMU planters complete and flatwork prep begins.
- NE Retaining wall dampproofing.
- A Ave. alley entrance demo and site work begins.
- 6/24 & 6/25 3rd St - demo and concrete for installation of irrigation sleeves. North end of 3rd St at A Ave will be closed. South portion of 3rd St will be accessible from Evergreen Rd.
June 6 - 12
- Installation of 4th St. MH-01 and catch basin. - - NOTE: A portion of 4th Street between A Ave and Evergreen Road will be closed Wednesday-Friday 7am-4pm. Access will be maintained from A Ave to the commercial parking garage at 4th and A and the lower City Hall Parking lot from Evergreen Rd.
- Formwork and reinforcing for retaining wall (center).
- Excavate for retaining wall footing (SW).
- NE Retaining wall close-up formwork.
- CMU at planter walls begin.
- Stair #5 elevator inspection and training.
March 31 - June 5
- Excavate for retaining wall footing (center).
- Backfill at storm planter walls.
- NE retaining wall boardform assembly continues.
- NE retaining wall reinforcing starts.
- CMU Planter footings form/reinforce/pour.
- Clean-out and removal of Baker tank on Evergreen Dr.
May 24 - 29
- Storm Water Planter walls form, reinforce and pour.
- Underground Storage Tank installation. Crane onsite at 0900 Monday 5/24, the north exit lane for the parking lot will be blocked for approximately 3 hours. HSW will have spotters in place for traffic movement.
- UST mechanical component installation.
- Testing & inspection of fuel & power lines to generator from UST.
- NE Retaining wall Boardform assembly begins.
- Storm Water Planter walls formed and poured.
May 17 - 22
- Installation of upper parking lot underground utilities.
- Excavation for storm water planter footings.
- Excavation for underground storage tank begins.
- NE Retaining wall footing rebar installation and concrete pour.
- Storm Water Planter footings form, reinforce and pour.
May 10-15
- Pour trash enclosure footing
- Trash enclosure wall forming & reinforcing
- Excavate NE retaining wall
- Being upper parking lot backfill
- Complete stair #5 wheelchair lift
April 26 - May 1
- Finish building demolition and debris removal.
- Concrete slab removal and perforation (this will be noisy).
- Preparation for concrete and backfill activities.
- 1st floor ballistic glass replacement.
April 12 - 17
- Demolition of the old City Hall continues
- Punch list items continue
April 5-10
- Disconnection and abandonment of the 6” fire line and the 1.5” domestic line (4-7 a.m., April 5)
- Demolition of the old City Hall to begin
- Final punchlist activities.
- Courtroom furniture delivery & installation.
- Remaining existing building utilities disconnected.
March 29- April 3
- Fencing installed around the old City Hall, garage and upper parking lot (March 31)
- North half of the northbound lane on 4th Street between A Ave and Evergreen will be closed (March 31)
March 22 -27
- Final punchlist activities.
- Traffic Control measures set-up for Phase 2 work around the existing city hall and 4th Street
- Tree removal along 4th and A Ave.
- Temporary alley asphalt installation.
- Courtroom furniture delivery & installation.
March 1 - 6
- Interior punchlist continues.
- Fitness Room Mirror Installation.
- Final Flooring Installation.
- Signage install completes.
- Final commissioning of building equipment.
- Site paver installation.
- Site clean-up and 3rd street cleaning.
- Building Inspection & Testing:
- Elevators
- Fire Alarm / Life Safety
- MEP Permits
- Building Final Inspections
After several days of delay due to inclement weather and power outage, the contractor is back to work. Below if the scheduled for the upcoming week.
Feb 22 - 27
- Interior painting continues.
- Temporary ADA Ramp construction begins.
- Building equipment training continues.
- 1st floor tile installation Completes.
- Exterior limestone installation completes.
- Countertop installation completes.
- Exterior wood paneling installation continues.
- Garage striping and parking bumper install.
- Interior glazing and mirror installation completes.
- Appliance connections.
- Interior signage installation.
- Vestibule flooring begins.
- Smoke barrier door installation.
- Movable partition installation and wood panel hanging continues.
- Life Safety system pre-testing.
Feb 8 -13
- Interior painting continues.
- 2nd floor wood ceiling installation completes & Level 1 wood ceiling begins.
- Installation of remaining Equitone panels continues.
- Building equipment commissioning & training continues.
- 2nd floor tile installation begins.
- SW site corner grading for site sidewalks.
- Underground prep for site concrete/sidewalks.
- Exterior limestone installation continues.
- Countertop installation completes.
- Exterior wood paneling installation begins.
- Toilet accessories installation continues.
- Stair #4 SS handrail installation.
- Garage striping and parking bumper install.
Feb 1 -6
- Level 3 flooring installation continues.
- Interior painting continues.
- 2nd floor wood ceiling installation begins.
- Installation of remaining Equitone panels continues.
- Building equipment commissioning & training continues.
- 3rd floor tile installation continues.
- SW site corner grading for site sidewalks.
- Underground prep for site concrete/sidewalks.
- Exterior limestone installation continues.
- Countertop installation completes.
- Exterior wood paneling installation begins
- Toilet accessories installation continues
Jan 25 - 30
Crews are working hard in anticipation of having a temporary certificate of occupancy issued by the end of February. The following work continues:
- Level 3 flooring installation
- LOCOM Server Room work space infrastructure installation
- Interior painting
- Installation of interior glazing & caulking
- 3rd floor wood ceiling installation
- Installation of east elevation Equitone panels
- Building equipment start-up and commissioning
- 3rd floor west corridor flooring begins.
- Interior and exterior limestone installation
- North elevated trench drain and sidewalk placement.
- 3rd floor casework and countertop installation
Jan 11 - 16:
- Interior wall and ceiling gyp. board finishing continues throughout.
- Install ceiling tiles on level 3 continues.
- Level 1 and 2 flooring installation continues.
- LOCOM Server Room work space infrastructure install continues.
- Interior painting continues.
- Installation of Storefront/Curtainwall and punch window glazing continues.
- Installation of East elevation Equitone panels.
- Building equipment start-up continues.
- 3rd floor restroom tile installation.
- 3rd Floor wood ceiling installation begins.
- Garage insulation continues.
- Installation of interior glazing begins.
- 1st floor interior specialties installation (corner guards, etc.).
- 2nd and 3rd floor casework continues.
Dec 28 - Jan 2 (Project site closed on January 1)
- Interior wall and ceiling gyp. board finishing continues throughout.
- Install ceiling tiles on level 2 continues.
- Generator start-up & training.
- Elevator #2 installation continues.
- Level 1 flooring installation continues.
- LOCOM work space infrastructure install continues.
- Interior painting continues.
- Installation of Storefront/Curtainwall and punch window frames and glazing continues.
- Installation of north elevation Equitone panels continues.
- Building equipment start-up continues.
- 3nd floor restroom tile installation prep.
Dec 21 -26
- Interior wall and ceiling gyp. board finishing continues throughout.
- Install ceiling tiles on level 2 begins.
- Elevator #2 installation continues.
- LOCOM work space infrastructure install continues.
- Interior painting continues.
- Installation of Storefront/Curtainwall and punch window frames and glazing continues.
- Installation of north elevation Equitone panels starts.
- Building equipment start-up continues.
- Low roof parapet waterproofing continues
- 2nd floor restroom tile installation continues.
- Generator start-up on 12/21, owner training on 12/22.
- Carpet installation on level 1 starts.
Dec 14 - 19
- Interior wall and ceiling gyp. board finishing continues throughout.
- Install ceiling tiles on level 1 begins.
- LOCOM RAF grounding.
- Elevator #2 installation continues.
- High roof gutter and downspout installation continues.
- LOCOM work space infrastructure install continues.
- Interior painting continues.
- Installation of Storefront/Curtainwall and punch window frames and glazing continues.
- Installation of west elevation Equitone panels continues.
- Building equipment start-up continues.
- Low roof paver installation.
- 1st floor restroom tile installation continues.
- North site stair forming and concrete placement.
- A Avenue sidewalk and curb demo – between alley and 3rd St corner.
Nov 30 - Dec 5
- Interior wall and ceiling gyp. board finishing continues on level 3.
- Elevator #2 installation continues.
- LOCOM work space infrastructure install continues.
- LOCOM prep for finishes and furniture installation.
- Interior painting continues.
- Installation of Storefront/Curtainwall and punch window frames and glazing continues.
- Installation of west elevation Equitone panels continues.
- Floor polishing continues.
- Building equipment start-up continues.
- South site stair concrete continues.
Nov 23 - 28
- Interior wall and ceiling gyp. board finishing continues on level 3.
- Elevator #2 installation continues.
- High roof gutter and downspout installation continues.
- LOCOM work space infrastructure install continues.
- Interior painting continues.
- Installation of Storefront/Curtain wall and punch window frames and glazing continues.
- Installation of south elevation Equitone panels continues.
- Building equipment start-up begins.
- Lower level floor polishing beginning.
- South site stair concrete continues.
Nov 2 - 7
- Interior wall gyp. board finishing continues on level 3 and stairwells.
- Elevator #1 installation and adjustment continues.
- Elevator #2 installation begins.
- High roof gutter and downspout installation continues.
- Raised access floor installation.
- Application of anti-graffiti coatings
- Interior painting on level 3 continues.
- Exterior painting of steel begins.
- Installation of Storefront and punch window frames and glazing continues.
- Installation of Equitone panels begins.
- Building water supply lines tied-in and tested.
- Natural gas line and NW Natural meter install.
- South elevation concrete work begins.
Oct 26 - 31
- Interior wall gyp. board installation continues on level 3.
- Elevator #1 adjustment continues.
- Interior painting on level 3 continues.
- Light fixture installation continues.
- Exterior canopy steel installation continues.
- Installation of storefront and punch windows on south and west elevations.
- PV roof panel installation continues.
- Fuel oil line installation begins.
Oct 19 -24
- Interior wall gyp. board finishing continues on level 3 and stairwells.
- Elevator #1 installation and adjustment continues.
- High roof gutter and downspout installation continues.
- Raised access floor installation.
- Interior painting on level 3 continues.
- High roof soffit panel installation begins.
- Installation of precast stair treads begins.
- Installation of Storefront and punch window frames and glazing continues.
- Delivery of Equitone panels scheduled.
- Installation of Clackamas county fiber vault and associated conduits.
- Natural gas line sleeve installation for NW Natural meter install.
Oct 12 - 17
- Elevator #1 installation continues.
- Gyp. board installation and finishing in level 3 continues.
- Interior painting on level 3 continues.
- Light fixture installation continues.
- High roof gutter and downspout installation continues.
- Exterior canopy steel installation continues.
- Installation of storefront windows on south and west elevations.
- Installation of punch windows on north and east elevations.
- PV roof panel installation continues.
Oct 5 - 10
- Interior wall gyp. board installation continues on level 3.
- Elevator #1 installation continues.
- Gyp. board taping and finishing in level 3 continues.
- Interior painting on level 1 continues, starts on level 2.
- North site stair forming continues.
- Light fixture installation continues.
- High roof metal panel installation continues.
- Steel canopy installation.
- High roof gutter and downspout installation continues.
- Exterior canopy steel delivery and installation.
- Installation of storefront windows on south and west elevations.
- Installation of punch windows.
- PV roof panel installation continues.
- Potholing for Clackamas Co. fiber vault.
Sept 28 - Oct 3
- 3rd St. replacement activities: The roadway work is anticipated to be completed by Friday, October 2.
- Fine grade Prep for AC paving.
- Asphalt pavement 1st of 2 lifts. Final lift will be the fall of 2021 after Phase 2 of construction is completed.
- Asphalt Testing.
- Street sweeping.
- Demobilize.
- Interior wall gyp. board installation continues on level 3.
- Elevator #1 installation continues.
- Gyp. board taping and finishing in level 3.
- Interior painting on level 1 continues, starts on level 2.
- North site stair forming continues.
- High roof metal panel installation continues.
- High roof gutter and downspout installation continues.
- Installation of 1st floor ceiling grid.
- Exterior canopy steel delivery and installation.
- Installation of punch and storefront windows on south and west elevations.
- PV roof panel installation continues.
3rd Street will remain closed until the roadway reconstruction work is completed.
A Avenue, the southern west-bound lane will be closed this week for construction activities.
Sept 21 - 26
- 3rd Street replacement activities for two weeks (9/21 - 10/5)
- NOTE: While this work is being done, adjoining roadways may have temporary road closures (but open to local traffic). Flaggers will be on site to direct traffic as needed. Please observe detours and drive safely.
- Survey and layout.
- Saw cutting.
- Surface and subgrade removal (
- West curb form and pour.
- Interior wall gyp. board installation continues on level 3.
- Elevator #1 installation continues.
- North boardform wall backfill (Mon. and Tues.).
- Gyp. board taping and finishing in levels 2 and 3.
- Interior painting on level 1 continues, starts on level 2.
- North site stair forming begins.
- High roof metal panel delivery and installation begins.
- High roof gutter installation begins.
- Installation of stair #3 precast treads continues.
- Exterior canopy steel delivery and installation.
- Installation of punch windows on south and west elevations.
- PV roof panel installation continues.
- PGE transformer installation in the lower parking lot of the existing City Hall.
Sept 8 - 12
- High roof installation continues.
- Interior wall gyp. board installation continues on levels 2 and 3.
- Elevator #1 installation continues.
- Installation of exterior skin support framing continues.
- Gyp. board taping & finishing on levels garage, 1, and 2 continues.
- Interior painting continues.
- Low roof PV panel delivery.
- North boardform wall backfill.
- Installation of stair #3 precast treads and handrails begins.
- Window frame installation begins on south and west elevations.
The site will be closed early (noon) on 9/4 and all day on 9/7 in observance of Labor Day.
Aug 31 - Sept 5
- High roof installation continues
- Interior wall gyp. board installation continues on levels 2 and garage.
- Elevator #1 installation continues.
- MEP ceiling and wall rough-in level 3.
- Exterior east elevation AWB continues.
- Installation of exterior skin support framing continues.
- Gyp board taping & finishing on level 1 and 2.
- Prime & 1st coat of wall/ceiling paint continues on 1st floor.
- North boardform wall pours on 8/31 and 9/2.
Road closures on 3rd St. through the remaining week will be for material delivery and will be as brief as possible.
Aug 24 - 29
- High roof installation continues.
- Interior wall gyp. board installation continues on levels 2 and garage.
- Elevator #1 installation continues.
- MEP ceiling and wall rough-in on level 3.
- Exterior AWB continues.
- Installation of exterior skin support framing continues.
- Gyp. board taping & finishing on level 1 and 2 continues.
- Interior painting continues.
- Low roof PV panel installation begins.
- North boardform wall inspections, close-up and pour.
Aug 17 - 22
- High roof installation begins.
- Interior wall gyp. board installation continues on levels 2 and garage.
- Elevator #1 installation continues.
- MEP ceiling and wall rough-in level 3.
- Exterior AWB continues.
- Installation of exterior skin support framing begins.
- Gyp board taping & finishing on level 1 continues.
- Polished concrete floor mock-up.
- Prime & 1st coat of wall/ceiling paint starts.
- North board form wall forming and rebar installation.
Aug 10 - 16
- Exterior wall sheathing continues.
- Exterior wall insulation continues.
- Interior wall gyp. board installation continues.
- Electrical room gear installation continues.
- MEP Wall rough-in levels 2 and 3.
- Exterior AWB installation continues.
- Elevator #1 installation continues.
- Drywall taping begins on level 1.
- Close-up and pour scabbed on north stair wall.
- Close-up and pour chimney footing and equipment pads in garage.
- Stripping of scabbed on board form wall.
Sidewalk and Roadway Impacts:
- 3rd Street - Sections of the roadway may be temporarily closed or blocked during some of the ongoing work and for deliveries. Please use caution when using the sidewalk or roadway.
Aug 3 - 8
- Low Roof Installation completes.
- Exterior wall sheathing continues.
- Exterior wall insulation continues.
- Interior wall gyp. board installation continues.
- Electrical room gear installation continues.
- Stairwell and elevator shaft framing, all levels.
- MEP Wall rough-in all levels.
- Exterior AWB installation continues.
- Elevator #1 installation begins.
- Drywall taping begins on level 1.
- Intumescent painting completes.
- Close-up and pour scabbed on north stair wall.
Sidewalk and Roadway Impacts:
- 3rd Street - Sections of the roadway may be temporarily closed or blocked during some of the ongoing work. Please use caution when using the sidewalk or roadway.
July 27 - Aug 1
- High roof installation begins.
- Delivery and installation of low roof solar panels begins.
- Interior wall gyp. board installation continues.
- Elevator #1 installation to begin.
- MEP ceiling and wall rough-in all levels.
- Remaining stairwell and shaft framing completes.
- North Scabbed on wall rough-in and reinforcing installation.
July 20-27
- Low Roof Installation completes.
- Exterior wall sheathing continues.
- Exterior wall insulation continues.
- Interior wall gyp. Board installation continues.
- Stairwell and elevator shaft framing, all levels.
- MEP Wall rough-in all levels.
- Stair #4 stringer installation.
- Elevator material delivery.
- North wall footing stripping and partial backfill.
- Exterior AWB installation starting.
Sidewalk and Roadway Impacts:
- 3rd Street - Sections of the roadway may be temporarily closed or blocked during some of the ongoing work. Please use caution when using the sidewalk or roadway.
July 13 -17
- Low Roof installation continues.
- Exterior wall sheathing continues.
- Interior wall gyp. board hanging.
- Shaft wall framing, all levels, continues.
- MEP Wall rough-in, levels 2 and 3.
- Overhead MEP rough-in on level 3.
- MEP Priority walls and interior partition framing on level 3.
- North exterior stair formwork and rebar install.
- North exterior stair footing concrete pour (7/15 or 7/16)
- Building power equipment installation.
- Low Roof AWB install.
Sidewalk and Roadway Impacts:
- A Ave - The south westbound lane will be closed 7:00 am - 3:00 pm on Thursday (7/16) while the north concrete stair footing is poured next to A Ave.
- 3rd Street - Sections of the roadway may be temporarily closed or blocked during some of the ongoing work. Please use caution when using the sidewalk or roadway.
July 6 - 10
- Roofing Installation continues.
- Exterior wall sheathing continues.
- Exterior wall insulation continues.
- Roof drain connections.
- Interior wall gypsum board installation continues.
- Stairwell and elevator shaft framing, all levels.
- MEP Wall rough-in all levels.
- North exterior wall waterproofing and footing formwork starting.
Sidewalk and Roadway Impacts:
- 3rd Street - Sections of the roadway may be temporarily closed or blocked during some of the ongoing work. Please use caution when using the sidewalk or roadway.
In observance of the July 4th Holiday, there will be no work on Friday, July 3 or the weekend.
June 29 - July 3
- Roofing installation continues.
- Exterior wall sheathing starting.
- Interior wall gyp. Board hanging start (pending sufficient water barrier from roof).
- Exterior wall insulation install start (pending sufficient water barrier from roof).
- Shaft wall framing, all levels, continues.
- MEP Wall rough-in, levels 2 and 3.
- Overhead MEP rough-in on level 3.
- MEP Priority walls and interior partition framing on level 3.
- North exterior stair underground utilities and formwork starting.
- 3rd Street waterline chlorination.
Sidewalk and Roadway Impacts:
- 3rd Street - Sections of the roadway will be temporarily closed during some of the waterline replacement work. Please use caution on the roadway during this work
June 22 - 26
- Roofing material delivery and installation
- 3rd Street Waterline – Early work package and Phase 2
- Demo existing reducer sleeves.
- Pre backfill inspections.
- Chlorination testing.
- Backfill and repair asphalt.
- Shaft wall framing, all levels.
- Door frame installation on levels 2 and 3.
- Interior partition framing on all levels.
- Intumescent painting on levels 2 and 3.
- North exterior stair footing excavation waterproofing.
Sidewalk and Roadway Impacts:
- A Ave - The south westbound lane will be closed 7:00 am - 3:00 pm Monday - Friday this week.
- 3rd Street - Sections of the roadway will be temporarily closed during some of the waterline replacement work. Please use caution on the roadway during this work.
June 15 - 19
- Roofing installation beginning. Tanker trailer to be parked at the NE corner of the site, near the stair tower.
- Garage MEP Wall rough-in.
- Interior partition framing on levels 1, 2, and 3.
- Layout & Frame MEP Priority walls on level 3.
- 3rd Street waterline – Early Work Package and Phase 2
- Tie-in phase 1 and phase 3 and energize lines.
- Pothole / Excavate for new pipe.
- Install Straddle blocks at valves.
- Isolate & remove existing pipe and valves.
- Install new tapping sleeves for chlorination operation.
- Excavate for north stair footings.
- Waterproof north exterior wall.
Sidewalk and Roadway Impacts:
A Ave - The south westbound lane may be closed 9 am - 3 pm during the excavation work with the north stair footing.
3rd Street - Sections of the roadway will be temporarily closed during some of the waterline replacement work. Please use caution on the roadway during this work.
A Avenue lane closure: The south westbound lane of A Ave will be closed for sanitary sewer line and other construction work this week on the following days.
- Wednesday (6/10) - 9 am - 3 pm
- Thursday (6/11) - 9 am - 3 pm
- Friday (6/12) - 9 am - 1 pm
June 8 - 12
- Delivery and installation of roof equipment. Crane scheduled to be set up on 3rd street for delivery on 6/11 and 6/12.
- 3rd Street waterline – Phase 3 and Early Work Package.
- Tie-in of new water service to west sidewalk meter box.
- Street Asphalt temporary repair.
- Chlorination of new waterline (Monday – Wednesday).
- Off Hours water shutdown of Bank of America, Goodyear Tire, Key Bank, for installation of new water valve scheduled for Wednesday (6/10) evening, from 5:00pm to 9:00 pm.
- Garage framing and MEP wall rough-in.
- Stairwell framing starting.
- Level 2 overhead MEP rough-in.
- Level 2 and 3 intumescent painting.
- F/R/P chimney wall footing.
- F/R/P MDS equipment pad.
- Pouring of tie-back block-outs in garage.
Sidewalk and Roadway Impacts:
3rd Street - Sections of the roadway will be temporarily closed during some of the waterline replacement work. Please use caution on the roadway during this work.
June 1 - 5
Thursday 6/4 - City crews will be replacing an old water valve at 3rd & Evergreen. This work was unexpected and only discovered after excavation. This work will require a temporary water service shut down from approximately 9:00 am - 3:00 pm to the residential apartments at 250 and 258 Evergreen Road. The contractor and city crews have notified the property owner who in turn have notified tenants. This temporary shut down also allows the apartment complex to do plumbing work they were planning on doing.
- Delivery and installation of roof equipment curbs. Small crane to be set up on 3rd street for delivery on 6/2 and 6/3.
- 3rd street waterline, Phase 1 street patch and begin Phase 3 (3rd & Evergreen).
- Exterior wall framing and sheathing.
- Low roof wall framing below high roof gables.
- Garage level tie-back repairs. Concrete scheduled for Thursday 6/4.
- Door frame installation on levels 1 and 2.
- Level 1 and 2 intumescent painting.
- Level 2 overhead MEP rough-in.
- North exterior stair wall excavation and mock-up.
Sidewalk and Roadway Impacts:
3rd Street - Sections of the roadway will be temporarily closed during some of the waterline replacement work. Please use caution on the roadway during this work.
In observance of memorial day, there will be no work on Monday, May 25
Construction activity the week of May 25 - 29 and Saturday May 30:
- Phase 1 of 3rd St. waterline replacement valve assembly and chlorination. New water connection to 334 3rd Street which will require water shut down on Saturday 5/30.
- Garage and level 1 interior partition and stair shaft framing/sheathing.
- Intumescent fireproofing on levels 1, 2 and 3.
- MEP priority wall framing on level 1 and 2.
- Level 2 overhead MEP rough-in.
- Exterior wall framing and sheathing.
Sidewalk and Roadway Impacts:
- 3rd Street - Sections of the roadway may be temporarily closed during some of the waterline replacement work. Please use caution on the roadway during this work.
May 18 - 22
Construction activity this week:
- Exterior skin mock-up construction continues.
- Exterior wall framing starting on North and West elevations.
- Tie-back block-out concrete repairs in Garage.
- Interior wall framing in Garage and Level 1.
- Overhead MEP rough-in on Level 1.
- Door frame installation on Level 1.
- Intumescent fireproofing on Levels 1 and 2.
- Initial activities for 3rd St. waterline replacement (Water intercept, utility locates).
- Solar Panel support installation.
May 11 - 15
Construction activity this week:
- Exterior skin mock-up construction continues.
- Tie-back block-out waterproofing and concrete patching in Garage.
- Garage and Level 1 interior wall framing.
- Level 1 and 2 intumescent paint.
- Form/Reinforce/Pour Stair 4 interior board form wall and low roof curbs.
- Level 1 overhead MEP rough-in.
- Level 2 and 3 steel monokote.
- East stone wall footing waterproofing and formwork.
Sidewalk and Roadway Impacts:
- A Ave - Equipment will be delivered to the alley between the existing and new city hall. The sidewalk and one lane may be closed at times to facilitate the delivery, but should be for very short periods.
- 3rd Street - Concrete trucks will be delivering concrete for stair 4 and low roof curbs. Please use caution on the roadway during this work.
May 4 - 8
Construction activity this week:
- Low Roof MEP slab/deck rough-in.
- Low Roof concrete placement (5/7).
- Low Roof equipment curbs (5/7).
- Tie-back detensioning (pending level 2 concrete strength test).
- Garage CMU completing.
- Garage interior framing starting.
- Level 1 and 2 monokote steel.
- Level 1 MEP priority wall layout & framing start.
- Level 1 overhead MEP rough-in.
- Level 1 intumescent paint start.
- SW corner utility excavation.
Roadway Impacts:
3rd Street - Concrete trucks will be delivering concrete for the pour on Thursday (5/7). Please use caution on the roadway during this work.
April 27 - May 1
Construction activity this week:
- Level 3 MEP slab rough-in.
- Level 3 rebar & formwork installation
- 3rd floor concrete placement (4/30 and 5/1).
- Stair #1 and #2 pour (4/27, 1st floor to garage).
- Garage CMU continues.
- Shaft wall layout & framing in garage
- Garage shaft layout starting.
- Level 1 monokote starting.
- SW corner utility excavation.
- Utility easement stakeout (4/27).
- Low Roof MEP slab/deck rough-in.
Roadway Impacts:
3rd Street - Concrete trucks will be delivering concrete for the pours on 4/23 and 4/24. Please use caution on the roadway during this work.
April 20 - 24
Construction activity this week:
- 2nd floor concrete placement (4/23 and 4/24)
- Stair #1 and #2 concrete pour, 2nd floor down.
- Garage CMU walls continue
- Generator connections
- Shaft wall layout in garage.
- Level 3 MEP layout and slab rough-in.
- Underground power bends lower parking lot and inspection by PGE (4/20 and 4/21)
- Temporary patch lower parking lot and open for reuse.
Roadway Impacts:
3rd Street - Concrete trucks will be delivering concrete for the pours on 4/23 and 4/24. Please use caution on the roadway during this work.
April 13-17
Construction activity this week:
- Metal deck stud and steel connection welding.
- Garage rebar dowel install for CMU walls.
- Garage masonry starting.
- 2nd floor MEP rough-in prep for concrete pour.
- 2nd floor rebar installation.
- Stair #4 wall form construction.
- Boring for new transformer power in existing lower parking lot. Monday 4/13 – Wednesday 4/15, parking lot will remain accessible to vehicle traffic. Parking spaces affected will be blocked off through Wednesday.
Road Closures:
3rd Street - Business and residential driveways will remain open during construction. Use caution during the work hours of 7am - 6pm as the site will continue to receive deliveries and have construction equipment traffic. Vehicle traffic is encouraged to use alternative routes.
April 6 - 10
Construction activity this week:
- Rebar dowel layout and installation for CMU wall installation during the following week.
- West alley utility support and backfill operation. Sidewalk along jobsite on A Ave will be closed during this operation.
- SW corner excavation for underground utilities and site concrete work.
- Garage MEPF installation.
- Generator exhaust installation starting.
- Metal deck stud welding
- Steel connection bolting and welding
- Crane demobilizing no later than Tuesday morning.
- Garage door frame installation.
- Stair tower extension.
Road Closures:
3rd Street - A section of 3rd Street is closed between 7 am - 6 pm for the duration of the steel structure installation, which is tentatively scheduled to be completed by April 10. Access to residential and commercial driveways will remain open.
A Ave - The south lane of A Ave between 3rd & 4th St will be closed from 7 am - 5 pm during the alley work. The sidewalk along the north side of the project will also be closed. Work is expected to be complete by April 17.
March 30 - April 3
Construction activity this week:
- Steel erection in sequences 16 – 20.
- Steel final bolting and connections in sequences 10-16.
- Garage MEPF pipe installation.
- Waterproofing installation at west and north, as available.
Road Closures:
A section of 3rd Street is closed between 7 am - 6 pm for the duration of the steel beam installation, which tentatively scheduled to be completed by April 10. Access to residential and commercial driveways will remain open.
March 16 - 27
- Backfill at east elevation for crane mobilization. Crane mobilization (3/17/20).
- Hanger and pipe installation for MEP trades in garage.
- Concrete wall patching at west and north walls for waterproofing installation.
- Waterproofing installation at west and north, as available.
Road Closures:
A section of 3rd Street is closed between 7 am - 6 pm for the duration of the steel beam installation, which tentatively scheduled to be completed by April 10. Access to residential and commercial driveways will remain open.
March 9 - 13
- Form/Reinforce/Pour 1st floor last exterior concrete wall and topping slab ramp in garage.
- Steel erection mobilization and initial sequence of steel deliveries (Wednesday 3/11)
- Hanger installation for MEP trades in garage.
- Concrete wall patching at west and north walls for waterproofing installation.
Road & Sidewalk Closures:
- 3rd Street - A section of roadway will be closed between 7 am - 6 pm starting this week until the end of the month when the steel erection is completed. Access to residential and commercial driveways will remain open.
- A Avenue - new covered pedestrian pathway is installed and open to pedestrians.
March 2 - 6
Construction activity this week:
- Form/Reinforce/Pour 1st floor exterior concrete walls.
- Site clean-up and prep for steel deliveries/mobilization. Steel mobilization / installation will begin next week.
- Garage ramp topping slab pour.
- Hanger installation for mechanical, electrical and plumbing (MEP) trades in garage.
- 3rd Street - sanitary line trench compaction.
Road & Sidewalk Closures:
- 3rd Street - periodic closures during trench compaction and other work.
- A Avenue - new covered pedestrian pathway is installed and open to pedestrians.
Feb 24 - 28
Construction activity this week:
- Form/Reinforce/Pour 1st floor exterior concrete walls.
- Shoring and lagging modifications for waterproofing access.
- Stripping slab forms and re-shoring slab in garage.
- Delivery and installation of pedestrian covered walkways on A Ave. One lane of A Ave will be closed during this work.
- Sanitary manhole work at A Ave. & Alleyway (2/26 & 2/27). One lane of A Ave. will be closed during the day and overnight for this work.
- Transformer vault demo, plate removal, and excavation at north edge of site. (2/24).
Road & Sidewalk Closures:
- 3rd Street - Anticipated to be open, but they will continue to use the east side parking for temporary equipment and material storage during the sanitary work in A Ave, which should be completed this week.
- A Ave - Will require a one-lane closure during working hours while working on the sanitary line and installation of covered pedestrian walkway. The sanitary line will also require one over night lane closure during the work (2/26-2/27). There will be at least one east-bound lane open during all of this work.
Feb 17 - 21
Construction activity this week:
- Tree removal at SW corner of site, via city hall surface lot and top of parking structure (planned of 2/17 only)
- Form/Reinforce/Pour 1st floor exterior concrete walls
- 3rd Street lateral tie-in
- A Ave. sanitary line tie-in and repair
- Pedestrian covered walkways on A Ave. side walk (planned for 2/20)
Road & Sidewalk Closures:
- 3rd Street - A section of roadway may be closed during sanitary lateral work.
- A Ave - Will require a one-lane closure during working hours while working on the sanitary line and installation of covered pedestrian walkway. The sanitary line will also require one over night lane closure during the work. There will be at least one east-bound lane open during all of this work.
Feb 5 - Project Update - A Ave & 3rd Street Traffic Change
Tomorrow (Thursday 2/6) between 9:00 am – 3:00 pm, PGE will be working at the intersection of A Ave and 3rd Street. East and west bound lanes at this intersection will be reduced to one lane. Flaggers will direct traffic during this work.
Next week the contractor will be working at the intersections of A Ave and 3rd Street and 4th Street to finish the switchover of power to the traffic signals.
Feb 3 - 7
Construction activity this week:
- Pour concrete south deck Monday (weather permitting)
- Cure time for beams and slab
- Remove ceiling forms and reshore
- Set forms and wall braces on the east
- Install rebar
Road & Sidewalk Closures:
- 3rd Street - A section of roadway may be closed during the concrete pour for the concrete pumper truck with flaggers directing traffic and alternative routes in place.
Jan 27 - Jan 31
Construction activity this week:
- Install deck form in preparation for Wednesday or Thursday concrete pour (weather permitting)
- Mechanical, electrical & plumbing layout
- Cure time for beams and slab
- Remove ceiling forms and reshore
- Set forms and wall braces on the east
- Install rebar
Road & Sidewalk Closures:
- 3rd Street - A section of roadway may be closed during the concrete pour for the concrete pumper truck with flaggers directing traffic and alternative routes in place.
Jan 20 - Jan 24
Construction activity next two weeks:
- Install deck form in preparation for concrete pour:
- First floor North slab is tentatively scheduled for Tuesday (1/21) weather permitting.
- First floor South slab is tentatively scheduled for Saturday (1/25) or early next week, weather permitting.
- Mechanical, electrical & plumbing layout
Road & Sidewalk Closures:
- 3rd Street - A section of roadway may be closed during the concrete pour for the concrete pumper truck with flaggers directing traffic and alternative routes in place.
Jan 6 - Jan 17
Construction activity next two weeks:
- Install deck form in preparation for concrete pour - First floor slab is tentatively scheduled for Friday (1/17) and into next week
- Signal transformer relocation
- Form & pour exterior walls
- Mechanical, electrical & plumbing layout
Road & Sidewalk Closures:
- 3rd Street - Section of roadway may be closed during the concrete pour with alternative routes in place
December 30 - Jan 3 (No Work January 1)
Construction activity this week:
- Install deck form in preparation for concrete pour later in January
- Signal transformer relocation
- Form & pour exterior walls
- Mechanical, electrical & plumbing layout
Road & Sidewalk Closures:
- 3rd Street - Generally open, with some construction fencing encroaching into roadway. Please drive with caution.
December 16 - 27 (No work December 25)
Construction activity this week:
- Form & Pour Exterior Walls
- Mechanical, Electrical & Plumbing Layout
Road & Sidewalk Closures:
- 3rd Street - Generally open, with some construction fencing encroaching into roadway. Please drive with caution.
December 9 - 13
Construction activity this week:
- Form & Pour Exterior Walls
- Mechanical, Electrical & Plumbing Layout
Road & Sidewalk Closures:
- 3rd Street - Generally open, with some construction fencing encroaching into roadway. Please drive with caution.
December 2 - 6
Construction activity this week:
- Remove Dewatering Storage Tank (Monday 12/2)
- Build Wall Forms
- Install rebar at Exterior Walls
- Utility work A Ave sidewalk
Road & Sidewalk Closures:
- Evergreen Rd – One lane open during dewatering storage tank cleaning and removal. Flaggers will be on site to direct traffic.
- 3rd Street - Closed on the north end near A Ave, but available for access to Key Bank from Evergreen Rd.
- A Avenue Sidewalk - Closed on the east and west end near the construction zone. The sidewalk is expected to be closed for the next 2 weeks during the utility work on site abutting A Ave.
Nov 25 - 29
Construction activity this week: This will be a short work week - No work on Thursday and Friday
- Build Wall Forms
- Rebar at Exterior Walls
Road & Sidewalk Closures:
- 3rd Street:Closed on the north end near A Ave, but available for access to Key Bank from Evergreen Rd.
- A Avenue Sidewalk:Closed on the east and west end near the construction zone. The sidewalk is expected to be closed for the next 2-3 weeks during the work on site abutting A Ave
- A Avenue: One east-bound lane closed during
Nov 18 - 22
Construction activity this week:
- Plumbing rough-in North Slab
- Build Wall Forms
- Rebar at Exterior Walls
- Sanitary Line A Ave
Road & Sidewalk Closures:
- 3rd Street:Closed on the north end near A Ave, but available for access to the bank from Evergreen Rd.
- A Avenue Sidewalk:Closed on the east and west end near the construction zone. The sidewalk is expected to be closed for the next 2-3 weeks during the work on A Ave
- A Avenue: One east-bound lane closed during sanitary line work in A Ave
* * * * Final mat slab pour rescheduled to Thursday 11/4 * * * *
Site preparation and installation of rebar continues in anticipation of the final mat slab pour. Work is schedule to begin at 5:00 am and end around 8:00 pm.
The contractor will avoid working outside of the Code permitted working for the remainder of the project. Code permitted work times are 7:00 am -6:00 pm, Monday - Saturday.
Nov 11 - 15
Construction activity this week:
- Pour South Mat Slab (Thursday - weather permitting, Friday backup)
- Plumbing rough-in North Slab
- Build Wall Forms
- Rebar at Exterior Walls
- Sanitary Line A Ave (Tuesday/Wednesday)
- Install Traffic Signal Loops in Roadway
Road & Sidewalk Closures:
- 3rd Street:Closed on the north end near A Ave, but available for access to the bank from Evergreen Rd.
- A Avenue Sidewalk:Closed on the east and west end near the construction zone.Spotters will be available to assist with pedestrian traffic.
- A Avenue: One east-bound lane closed during sanitary line work in A Avenue
Nov 4 – 9
Construction activity this week:
- North Mat Slab:Wednesday (11/6) concrete pour from 5:00 am -8:00 pm
- South Mat Slab:Waterproofing trenches, rat slap and rebar installation in preparation for next Tuesday’s (11/12) concrete pour
- A Avenue sanitary
- Crews will be working on Saturday installing rebar and concrete in the utility trench in order to prepare the mat slab pour on Thursday (11/14).
Road & Sidewalk Closures:
- 3rd Street:Closed on the north end near A Ave, but available for access to the bank from Evergreen Rd.
- A Avenue Sidewalk:Closed on the east and west end near the construction zone.Spotters will be available on Wednesday during the mat slab pour to assist with pedestrian traffic.
Use caution when driving in the construction zone and follow all traffic signs.
* * * * Mat slab delayed to Wednesday 11/6 and Tuesday 11/12 * * * *
Crews have not been able to make up the time for the schedule impact from the previous week and will need to push the mat slab pours out another week. Site preparation and installation of rebar continues in anticipation of the new pour dates. Work is still schedule to begin at 5:00 am and end around 8:00 pm.
* * * * October 22 - Mat slab delayed to Wednesday 10/30 * * *
The first mat slab pour scheduled for Thursday 10/24 has been rescheduled to Wednesday 10/30. The second pour is now scheduled for Thursday 11/7. Work is still scheduled for 5 a.m – 8 p.m.
Crews will be busy preparing the site for the big pours by installing rebar and pouring an initial rat slab (thin layer of non-structural concrete poured over the compacted rock). The delay is due to the wet weather we experienced last week, which saturated the soil. This required a substantial amount of additional rock base to provide a stable compacted surface for the concrete. The additional time and effort to bring in the additional rock caused the schedule to be pushed out.
Oct 21 - 25
Activity happening this week:
- Excavation for utility trenches and elevator pits
- CDF backfill at lagging along A Ave. A concrete pumper and concrete trucks will be using A Avenue for this work.
- Water proofing at trenches
- Mass excavation and boulder removal
- Rat slap prep work
Road & Sidewalk Closures:
- 3rd Street - Currently open to traffic, but may be partially closed to through access during construction activity
- A Ave - One lane closure of the south lane on Tuesday (10/22) from 9 a.m. - noon for construction activity to backfill behind lagging. The sidewalk on the north side of the site will also be closed during this work. Please use alternative sidewalk routes.
Oct 15 Construction Activity Update - Concrete Pour 10/24 & 10/31, 5 a.m.. - 8 p.m..
We’re quickly coming up on a project milestone which is pouring the mat slab (concrete that extends over the entire building footprint.) This will be a major undertaking which will take two separate days, 10/24 and 10/31, working from 5:00 am – 8:00 pm. The second concrete pour date is on Halloween, however, all of the concrete trucks will be finished by noon and the site will be secured so it will not interfere with any evening activities.
Please click on the concrete pour link for more information and a site logistic map.
This work is subject to weather and other unforeseen conditions. Any changes to the date and time will be posted on this webpage.
Oct 14 - 18
Activity happening this week:
- PGE Transformer Relocation (Lower Parking Lot of Existing City Hall)
- Excavation for utility trenches and elevator pits
- Mass excavation and boulder removal
- Rat slap prep work
- Sanitary on A Ave
Road & Sidewalk Closures:
- 3rd Street - Currently open to traffic, but may be partially closed to through access when excavation or other activities begin
- A Ave - One lane may be closed during the sanitary work
Oct 7 - 11
Activity happening this week:
- Excavation for installation of final lagging installation
- Excavation for utility trenches and elevator pit
- Mass excavation and boulder removal
Road & Sidewalk Closures:
- 3rd Street - Currently open to traffic, but will be closed to through access when excavation begins.
September 30 – October 4
Activity happening this week:
- Sanitary sewer installation on 3rd Street and A Ave – work is anticipated to be completed by the end of October 11.
Road & Sidewalk Closures:
- 3rd Street - Closed to through access. Anticipated to be closed early in the week for sanitary work, but still accessible to the bank.
- A Avenue - One-lane closure between 6:00 am - 3:00 pm during the sanitary work. The south eastbound lane will remain close overnight Monday through Wednesday.
- The sidewalk on the south side of A Avenue between 3rd & 4th Street will be closed. Please use the sidewalk on the north side of A Avenue.
September 23 – 27
Activity happening this week:
- Finish grouting and tensioning tie backs
- Excavation and boulder removal
- Trench excavation for utilities
- Prepare for sanitary sewer installation on 3rd Street and A Ave – work is anticipated to begin by Wednesday (9/25)
Road Closures:
3rd Street - Closed to through access. Anticipated to be closed near the middle of the week for sanitary work, but still accessible to the bank.
A Avenue - One-lane closure between 7:00 am - 3:00 pm may be scheduled near the end of this week depending upon sanitary sewer work.
September 16 - 20
Activity happening this week:
- Demobilize crane
- Finish drilling, grouting and tensioning tie backs
- Excavation and boulder removal
- Prepare for sanitary sewer installation
Road Closures:
3rd Street - Closed to through access, but still accessible to the bank
A Avenue - One-lane closure between 7:00 am - 3:00 pm may be scheduled depending upon sanitary sewer work and removal of heavy equipment from the site
September 9 - 13
Activity happening this week:
- Mass Excavation
- Shoring Installation (lagging and tiebacks)
- Removal of piling drill rig
- Sanitary sewer utility exploration and design
Road Closures:
3rd Street - Closed to through access, but still accessible to the bank
A Avenue - One-lane closure between 7:00 am - 3:00 pm may be scheduled depending upon sanitary sewer work and removal of heavy equipment from the site
September 3 - 6
Activity happening this week:
- Mass Excavation
- Boulder Removal
- Shoring Installation
Road Closures:
- 3rd Street - Closed to finish sewer work
- A Avenue - At this time, closed Wednesday only, for manhole investigation. Additional closures may be scheduled depending upon manhole installation direction
As always, use caution when driving in the construction zone and follow all traffic signs.
The schedule may change as needed due to unforeseen circumstances and weather conditions.
August 26 - 30
Sanitary Sewer Line 3rd Street – Work should completed this week. Expect a 24-hour road closure on the north end of 3rd Street during this work. Key Bank parking signs will be placed on A Ave in front of the bank for customers.
Sanitary Sewer Line A Ave – Work is expected to begin later this week on the south lane of Ave and will last through August 30. The south lane on A Ave between 3rd Street and 4th Street will be closed between 6:00 am – 3:00 pm. This road closure will overlap with the road closure on 3rd Street.
Pile Installation – Pile drilling will continue this week and into next week. The work is going slower than expected because there is more rock on the site than expected.
As always, use caution when driving in the construction zone and follow all traffic signs.
The schedule may change as needed due to unforeseen circumstances and weather conditions.
August 19 - 23
- Sanitary Sewer Line 3rd Street – This week, crews are expected to finish the sanitary work on the north end of 3rd Street. Expect a 24-hour road closure on the north end of 3rd Street during this work. Key Bank parking signs will be placed on A Ave in front of the bank for customers.
- Sanitary Sewer Line A Ave – Work is expected to begin later this week on the south lane of Ave and will last through August 30. The south lane on A Ave between 3rd Street and 4th Street will be closed between 6:00 am – 3:00 pm.
- Pile Installation – Pile drilling will continue this week and into next week. The work is going slower than expected because there is more rock on the site than expected.
As always, use caution when driving in the construction zone and follow all traffic signs.
The schedule may change as needed due to unforeseen circumstances and weather conditions.
August 12 - 16
- Sanitary Sewer Line 3rd Street – work will be finishing up on the north end of 3rd Street. Beginning of the week, expect 24-hour road closure on the north end of 3rd Street during this work. Key Bank parking signs will be placed on A Ave in front of the bank for customers.
- Sanitary Sewer Line A Ave – Work will begin on the south lane of Ave next week and is expected to last into the week of August 19th. The south lane on A Ave between 3rd Street and 4th Street will be closed between 6:00 am – 3:00 pm. Use caution when driving on A Ave and follow all traffic signs.
- Pile Installation – Pile drilling will start on Monday (8/12) and continue into next week. Drilling the 72 piles on site has less impact than pile driving.
August 9
Join us in celebrating the groundbreaking for Lake Oswego’s new City Hall. The ceremony will take place at the construction site on A Avenue and 3rd Street on Friday, August 9. Welcome and program will begin at 11 a.m..
Scheduled activities include remarks from Mayor Kent Studebaker, and representatives from Mackenzie Architects and General Contractor Howard S. Wright, among others. Architectural renderings will also be displayed and light refreshments served. The event will wrap up with the traditional sod-turning ceremony.
The new City Hall will provide the community with a seismically safe, modern, energy efficient and better functioning building that will be designed to a LEED Gold rating standard. Construction is expected to be completed with move-in around March 2021. Final completion of the project is expected by the end of 2021.
The project has been many years in the making – please join us to mark this special occasion!
July 29 - August 9
Contractors will begin sanitary work that will include some temporary road closures. New sanitary line will be installed from Evergreen Road up 3rd Street and A Avenue along the project frontage. This work will last 3-4 weeks (subject to change due to unforeseen circumstances). Work to be completed in 4 phases with 24-hour road closure on sections of roadway where work is occurring. There is a possibility that one lane may remain open during non-work hours.
Access to all businesses and residences will remain available at all times. The sidewalk on the east side of 3rd Street will remain open. The sidewalk on the west side will be closed.
July 22 - 26
- Pot Hole Utilities
- Demolition of Hardscape
- Site Grading
July 10 - Site Preparation and Tree Removal
Deconstruction of the two buildings next to the existing city hall is wrapping up. Site preparation will continue as trees around the new city hall site are removed. Tree and shrub removal will begin possibly today at the north end of the site along A Avenue and move southward on the property. Sidewalks on A Avenue and Third Street will be closed during this work. All tree removal should be completed by Monday.
Once the new City Hall is built, new trees will be planted.
July 8 - Deconstruction
During the week of July 8 - 12, deconstruction will continue with pot holing for utilities, tree removal, silt fence and construction fencing installation, along with grading in preparation for pile installation.
July 1 - Demo Continues
June 24 - City Hall Deconstruction to Begin
June 24 marks the first visible milestone in the New City Hall project. On Monday buildings at the corner of A Avenue and Third Street will begin to be deconstructed to make room for the new building. The process is expected to take two to three weeks and be completed by mid-July. Some trees that pose a safety risk or impeded the deconstruction process will be removed. Most of the trees during this phase will be removed near the end of the deconstruction process. The sidewalk on A Ave will remain open, however portions of the sidewalk on 3rd Street will be closed. Parking will still be available on most of 3rd Street.
Material from the deconstruction of the buildings will be hauled to a regional material sorting facility in Wilsonville where wood, metal and masonry is separated and recycled. While the goal is to recycle 75% of materials, this project anticipates recycling over 90% of the materials.
June 4, 2019 - Fire Training at A Ave & 3rd St
June 5-7, the LO Fire Department will be conducting training in commercial buildings at the corner of 3rd Street and A Avenue (at 320 A Ave and 366 3rd St). Passersby can expect to see fire personnel, LOFD's ladder truck and 1-2 fire engines at the site from 9am-noon and 1:30-4:30pm each day.
Firefighters will be focusing on a variety of skills during this training, including search and rescue techniques, roof operations/ventilation, forcible entry, fire attack-hose deployment, water supply and ground ladder placement. There will be NO live fire as part of this training. This valuable training allows firefighters to hone their skills and prepare them better for emergency responses.
This location is where the new City Hall will be built. In addition to LOFD training, over the next few weeks you may see the LO Police Department and the Clackamas County SWAT team training at the site. After the training, deconstruction of the buildings will begin. Deconstruction is expected to start somewhere around mid-June. For more information about the City Hall project, visit www.ci.oswego.or.us/lora/new-city-hall-project or call the construction hotline at 503-635-0261.
For more information about the LOFD training, contact Gert Zoutendijk, Lake Oswego Fire Department, at 503-635-0275.
May 21, 2019 LORA meeting
At the meeting, the Board approved early work site preparation and material procurement in the amount of $8,107.796.00. This authorization locks in construction costs for approximately 25% of the project cost, reduces wet-weather impacts and keeps the project on schedule. The design team has completed 75% construction documents and anticipates completing 90% of this phase in early June. View the meeting materials.
April 1, 2019 DRC meeting
The DRC approved the Development and Conditional Use Permits and Design and Minor Variances to construct the new City Hall and associated parking. View the meeting on our YouTube channel. View the posted meeting materials.
March 5, 2019 LORA Meeting
With the design development phase drawings now completed, the Board approved the development phase drawings and authorized the team to move forward into the construction document phase. The meeting materials are posted online.
November 6, 2018 LORA meeting
The LORA Board approved the schematic design on Tuesday, November 6, 2018. View the meeting materials (design, floor plans, site plans). The next steps for the project will be to hold a pre-application conference, submit the land use application, meet with the Evergreen neighborhood association, and schedule a hearing with the Development Review Commission once the application is complete. The work includes further development of the design details both on the exterior and interior of the new building.
June 12, 2018
The LORA Board directed staff to proceed with the concept to construct a new city hall on the property next to the existing city hall building. A revised concept was approved by the Board on July 17. The meeting materials are posted online.
New City Hall Project Overview
The Lake Oswego Redevelopment Agency is working on the planning and design of a new City Hall in downtown Lake Oswego. The new City Hall will provide a seismically safe, energy efficient and better functioning building for the community and city staff. It will include space for all existing departments including police and 9-1-1 dispatch center, as well as public meeting places. It will also provide storefront space for the Lake Oswego Arts Council and the Friends of the Library’s “Booktique.” The new building will be 3 stories over one level for secured police parking.
The new city hall building will be built adjacent to the existing city hall in downtown Lake Oswego. After the new building is complete, the existing city hall will be demolished and replaced with a new civic plaza, surface parking and street improvements.
The majority of the project is funded by urban renewal.
Police Facility Background
The city has studied the siting and construction of a new police facility since 2001. The current space on the second floor of City Hall has long been recognized as inadequate for housing Police and 911 dispatch services. The building cannot be secured, there is insufficient space for police operations, and the building does not meet current seismic standards for essential services.
Following several site studies, needs assessments, and condition analyses, in 2013 the Lake Oswego City Council, acting as the Lake Oswego Redevelopment Agency (LORA) Board, decided to purchase the three privately-held parcels immediately east of city hall as the site for a new police and 911 facility. The properties were acquired in 2015 and 2016. Following the decision to replace city hall, rather than just build a new police facility, a new city hall will be constructed on the properties next door to the existing city hall.
City Hall Background
The existing Lake Oswego City Hall, value-engineered and constructed in 1986 for about $5 million, has multiple and significant building and programmatic deficiencies identified through several studies and condition assessments.
The inadequate drainage system of the building, compounded by the long history of excessive amounts of rainwater penetrating through the building's envelope (an EIFS cladding system), has damaged the underlying components of the building’s exterior wall. It is no longer feasible to maintain the building envelope and the lack of drainage system coupled with the significant concealed damage under the EIFS cladding removes the possibility of doing targeted repairs. An assessment conducted in July 2015 recommended a full replacement of windows, doors, EIFS and underlining sheathing and insulation, roof, and repairs to the exterior walls. Additionally, the building's systems such as the HVAC, generator, and elevators are in need of replacement.
A seismic and structural assessment of the building noted that the structure would not perform well in an earthquake and the cost to retrofit the building would compare to the construction of a new facility. On March 21, 2017, the City Council decided to build a new City Hall with urban renewal funds rather than making the costly repairs and affirmed that decision on June 12, 2018.