Project Timeline & Concept Design Delete
An expected timeline for the South Shore Fire Station project and concept drawings were discussed at the February 3, 2026 City Council meeting.
Expected Timeline
- February 17, 2026: City Council adopted Resolution 26-08, directing staff to submit to the voters at the May 19, 2026 Election, a measure authorizing issuance of general obligation bonds in an amount not to exceed 20.6 million to finance the replacement of the South Shore Fire Station.
- May 19, 2026: Voters will consider a proposed bond measure for this project.
- February 2027: If the proposed bond is passed, construction on a new South Shore Fire Station could begin in early 2027. If the proposed bond is not passed, the City will not construct the facility.
- Early-mid 2028: If the bond is passed, construction could be complete by early 2028.
Project Schedule (as of February 3, 2026)