Project Updates
October 2026: South Shore Fire Station Update
Project Status: Schematic Design is complete and the cost estimating has begun. Once the estimate is complete, the team will value engineer design decisions to remain on track and under budget.
Schedule: The Land Use Application for the Temporary Station has been submitted. Land Use Application for the New Fire Station will be submitted in October.
Completed:
- Arts Council Steering Committee for Public Art Selection Created
- Design Package review with City Facilities, IT, and Fire Steering Committee
- Initial Meeting with Energy Trust of Oregon
Still to be completed:
- Arborist Reports for both applications
- Hazardous Materials Inspection in permanent station prior to demolition
- Schematic Design Cost Estimate
Council Updates:
2026
October 20 Council Study Session
December 15 Council Study Session
2027
February 16 Council Study Session
April/ May Guaranteed Maximum Price Decision
June 1 Council Study Session
October 19 Council Study Session