October 2026: South Shore Fire Station Update

Project Status: Schematic Design is complete and the cost estimating has begun. Once the estimate is complete, the team will value engineer design decisions to remain on track and under budget.

Schedule: The Land Use Application for the Temporary Station has been submitted. Land Use Application for the New Fire Station will be submitted in October.

Completed:

  • Arts Council Steering Committee for Public Art Selection Created
  • Design Package review with City Facilities, IT, and Fire Steering Committee
  • Initial Meeting with Energy Trust of Oregon

Still to be completed:

  • Arborist Reports for both applications
  • Hazardous Materials Inspection in permanent station prior to demolition
  • Schematic Design Cost Estimate

 

Council Updates:

2026

October 20                Council Study Session
December 15            Council Study Session

2027

February 16               Council Study Session
April/ May                  Guaranteed Maximum Price Decision
June 1                        Council Study Session
October 19                 Council Study Session

 

 