Third Street Project
The City of Lake Oswego is repairing the sidewalk and pathway leading across the Rail Road tracks at the end of Third Street. The project will bring the sidewalk into compliance with ADA standards.
February 12, 2015
Construction is scheduled to begin Saturday, February 14, 2015, 8:00 AM.
- Pathway will be closed to through traffic, while Contractor is working on site. The Pathway will be open for use during non-working hours.
- They will start with demolition of sidewalk and pathway.
- Re-grading, forming, and pouring concrete will take place next week.
Check back next week for additional updates.
February 2015
The City is currently in the process of hiring a contractor to perform the work. The project is scheduled to begin sometime in January. During construction there will be short periods when the pathway will be closed for construction, we ask that you use alternate routes during those times.
Please check back in a couple of weeks for specific closure times.
David Kudna, Project Manager - 503-534-5299 or dkudna@ci.oswego.or.usSi